NERC Committee Approves Data Center Ride-Through Project, RTO Insider Says
NERC's Standards Committee approved Project 2026-03 on data center ride-through and power recovery, RTO Insider reported, after 3,800 MW of Northern Virginia load dropped on July 22.
2 min read

NERC's Standards Committee approved Project 2026-03, RTO Insider reported; the figures come from NERC's agenda package.
Illustration (AI-generated)
NERC's Standards Committee has approved a new project, numbered 2026-03, to write data center ride-through and post-fault power recovery requirements for computational loads, RTO Insider reported on Oct 21, 2026. No NERC standard sets such requirements for load today.
The project follows a pattern NERC documents in its committee agenda package. In July 2024, about 1,500 MW of data center load in the Dominion Energy Virginia area moved to backup generation after a 230 kV line fault, although no data center was disconnected by the fault itself. A February 2025 event in the same area removed about 1,800 MW across 18 substations. On July 22, 2026, about 3,800 MW dropped across Northern Virginia, more than double the 2024 figure. NERC calls these customer-initiated load reductions.

The July 22 event was the largest of three load reductions in the Dominion Energy Virginia area, according to NERC's agenda package.