Power · Oct 18, 2026, 16:55
Oracle's 1.3 GW Wisconsin AI campus set to miss 2027 target, Aterio says
Oracle's huge planned AI data center in Port Washington, Wisconsin, cannot run until state regulators approve its power line connection. Research firm Aterio expects real use to start only in 2028.