AI rack power and electricity cost estimator
What an AI rack, server or desk machine costs in electricity: a published power figure from the maker or an independent reviewer, a facility overhead from industry surveys and U.S. electricity prices from EIA. Every default carries its source and date; anything you type is marked as your input.
Estimate
NVIDIA DGX B200
An estimate, not a measurement or an expected bill: vendor maximum 14.3 kW of IT power, drawn every hour, facility power 21.7 kW, 190.4 MWh over 8,760 hours.
Commercial priceSourced
$26,733
a year at 14.04 cents per kWh
At the vendor maximum, every hour: an upper bound.
$0.381 per GPU-hour
Industrial priceSourced
$17,308
a year at 9.09 cents per kWh
At the vendor maximum, every hour: an upper bound.
$0.247 per GPU-hour
Non-IT facility load (cooling, power conversion, lighting): 7.44 kW, 34.2% of the facility's energy.
Range across the sourced choices: $6,519 to $26,733 a year, varying the stated figure and a 50% to 72.5% share worked out from LBNL's stated ranges (power while working from its 2024 report); PUE from 1.145 to 1.52; commercial and industrial prices.
How the estimate is worked out
- IT power = 14.3 kW × 1 server × 100% (the stated figure at every hour) = 14.3 kW
- Facility power = 14.3 kW × PUE 1.52 = 21.736 kW
- Non-IT facility load (cooling, power conversion, lighting) = 14.3 kW × (1.52 − 1) = 7.436 kW, 34.2% of the facility's energy
- Energy = 21.736 kW × 8,760 hours = 190,407.36 kWh
- Cost, commercial = 190,407.36 kWh × $0.1404 = $26,733
- Cost, industrial = 190,407.36 kWh × $0.0909 = $17,308
- Per GPU-hour, commercial = 21.736 kW × $0.1404 ÷ 8 GPUs = $0.381
- Per GPU-hour, industrial = 21.736 kW × $0.0909 ÷ 8 GPUs = $0.247
Electricity against the rental price
Electricity per GPU-hour (estimate): $0.381 at the commercial price, $0.247 at the industrial price.
Oracle Cloud's on-demand list price for the NVIDIA B200, the only one of the clouds we track (Microsoft Azure, Oracle Cloud, Google Cloud) with a recent price for it: $14.00 per GPU-hour, Oracle Cloud, all regions, read Nov 23, 12:01 UTC.
Electricity comes to 1.8% to 2.7% of that provider's list price. Other GPU clouds can list this GPU for less, which would push the share higher.
A list price also pays for the hardware, networking, the building and the provider's margin, so this is not the provider's cost. The cloud's NVIDIA B200 instances may run servers other than the NVIDIA DGX B200. Every GPU's cloud price
The figures behind it
- Power figure Sourced
- 14.3 kW per server: Vendor maximum (nameplate, not measured draw)
Source: NVIDIA, as of Oct 16, 2026. Stated as: ~14.3 kW max system power
- GPUs per server Sourced
- 8
Source: NVIDIA, as of Oct 16, 2026. Stated as: 8 Blackwell GPUs
- Units Your choice
- 1 server, a count you choose
- Average draw
- 100% of the figure: the stated figure at every hour
Upper bound: the maker's maximum, drawn at every hour. Real draw is lower.
Source: LBNL, 2024 U.S. Data Center Energy Usage Report, section 3, Server Power Draw, as of Dec 20, 2024.
servers rarely, if ever, actually draw the full wattage for which they are rated on specification sheets
- Facility overhead (PUE) Sourced
- 1.52: Industry average (Uptime Institute 2026 survey). Annual averages reported by operators worldwide, for data centers of every kind, not only AI halls.
Source: Uptime Institute, Global Data Center Survey 2026, p. 7, Figure 2 (n=644), as of Jul 28, 2026.
The 2026 industry average PUE is 1.52
- Electricity price
- Commercial: 14.04 cents per kWh Sourced
U.S. total, year to date through August 2026, preliminary.
Source: EIA, Electric Power Monthly, Table 5.6.B, as of Oct 23, 2026
Industrial: 9.09 cents per kWh SourcedU.S. total, year to date through August 2026, preliminary.
Source: EIA, Electric Power Monthly, Table 5.6.B, as of Oct 23, 2026
- Hours Your choice
- 8,760: a full year (365 days × 24 hours)
About the electricity prices
- EIA's average price is a sector's revenue divided by its sales: it includes energy and demand charges, service charges, surcharges, fuel adjustments and taxes, and in EIA's words it
does not reflect the per kWh rate charged by the electric utility to the individual consumers.
EIA technical notes. A site's own contract can differ from these averages. - Utilities may class commercial and industrial customers by industry code or by their demand or usage, so a data center can be billed as either; the estimate shows commercial and industrial prices side by side.
- From EIA's Electric Power Monthly, released Oct 23, 2026 with data for August 2026; EIA's 2026 values are preliminary estimates from a sample. EIA's next scheduled release: Nov 24, 2026.
What the estimate leaves out
- The hardware itself, its depreciation, and the network and storage outside the system.
- Water, on-site generation, and any capacity or standby charges in a site's own contract.
- How the non-IT load splits between its parts: the published PUE figures do not separate them.
- For a desk machine, anything outside the machine itself.
Which systems are listed
A system is listed only with a whole-system power figure its maker or an independent reviewer has published, each shown with its source and date, and a reviewer's figure is credited to the reviewer. A maker's maximum is an upper bound on draw. A thermal design power is a design figure for the heat a system sheds, not a maximum. A power supply rating is the supply's output capacity: at full output the draw at the wall is higher by the supply's conversion loss. None of these is a measured draw; a reviewer's measurement holds for the load it names. A GPU's own board power, a chip's thermal design power or a chassis's thermal envelope is not used: each leaves out parts of the machine or is not an electrical figure, so a machine whose maker states only such a figure is not listed.