Oklo Reserves U.S. Forged Rings Capacity for Aurora Components From 2030
Oklo has reserved capacity at U.S. Forged Rings' planned North Carolina plant for large Aurora reactor components, with initial deliveries targeted for 2030. No value was disclosed, and the plant is not built yet.
Chips & Power DeskEdited by Ege Erten
3 min readAI-assisted
Follows our story: Oklo 10-Q: Meta Funds Paid to Centrus for HALEU, Deliveries From 2029

Image from Oklo's release on the U.S. Forged Rings agreement; it shows a large steel component, not a finished Aurora reactor vessel.
Image: Oklo
Source · Press image from the Oklo newsroom, used for news reporting.
Oklo said on Nov. 6 that it has reserved manufacturing capacity at U.S. Forged Rings' planned campus in Hertford County, North Carolina, for large Aurora reactor components, with initial finished component deliveries beginning in 2030, Oklo said.
The strategic manufacturing agreement reserves capacity for large components of the Aurora reactor module system. Oklo's release describes large stainless-steel parts such as reactor vessels, lids and supporting structures as hard to make, and its 10-Q lists them among the components covered. The reservation is meant to cover capacity through 2035, with options to expand it. Oklo's quarterly report for the period ended Sept. 30 dates the signing to October 2026 and describes the same terms. Oklo's release and 10-Q disclose no contract value, payment, or number of reactors' worth of components the reservation covers.

Oklo's fuel and heavy-component dates are company targets; the USFR plant is not yet built.
Illustration (AI-generated)
This is the components half of Oklo's supply chain. As Voltgrid reported, the same 10-Q says an initial Meta funding amount left escrow on Nov. 2 and was paid to Centrus as a credit toward high-assay low-enriched uranium (HALEU) fuel orders. Separately, a June 2026 letter of intent with Centrus expects HALEU deliveries to begin in 2029 for up to five Aurora powerhouses, and the Sept. 30 supply agreement is subject to certain conditions. Both the 2029 fuel and the 2030 components are Oklo targets, not delivered or ordered volume.
What the agreement covers
Oklo's Aurora is a metal-fueled, sodium-cooled fast reactor. Parts that large, Oklo said, can need several fabrication steps, shipping between suppliers, and extra welding, machining and inspection. U.S. Forged Rings (USFR) plans to put casting, forging, ring rolling, heat treatment, machining, fabrication and inspection on one site, next to domestic steelmaking, with rail and an on-site port for barging oversized parts. USFR chief executive Giacomo Sozzi said many of the largest steel components for nuclear reactors are now sourced overseas.
Oklo said the deal is separate from the procurement, manufacturing and construction already under way for its first Aurora powerhouse at Idaho National Laboratory. Oklo says the components are for future Aurora powerhouse deployments. Its January agreement with Meta supports a planned 1.2 GW campus in Pike County, Ohio, with a first phase targeted as early as 2030, but Oklo has not tied the USFR reservation to that campus or any other project.
The plant is still a plan
The North Carolina campus does not exist yet. When Governor Josh Stein's office announced the project on Feb. 26, 2026, USFR said the project would have three phases and a planned total investment of $875 million (the Governor's headline says "up to $875 million"), with the first two phases estimated to create 625 full-time jobs. The site sits beside Nucor Steel's Hertford County facility, and USFR, incorporated in March 2022 and owned by the Sozzi family's industrial group, has a supply-chain partnership with Nucor. Neither release gives a construction start or a date when the first phase will produce.
Why Reactor Components Need Reserved Capacity
A capacity reservation holds a place in a factory's schedule for parts that do not exist yet. Oklo says reactor vessels, lids and supporting structures are large stainless-steel pieces that can need several fabrication steps, shipping between suppliers and extra welding, machining and inspection, so it reserved capacity at U.S. Forged Rings' planned North Carolina campus, where those steps are to sit on one site.
The reservation is not an order. Oklo's release and 10-Q give no value, volume or payment, and say initial finished component deliveries are targeted for 2030, with capacity intended through 2035 and options to expand. For a buyer planning many reactors, the effect is on timing: heavy components can set the build schedule as much as the licence, and this one depends on a plant that has not been built.
What to watch
Oklo's 2030 delivery target depends on USFR building its planned plant first, and neither company has given a construction or production schedule. Oklo's 2026 annual report, expected in the first quarter of 2027, may show whether a commitment amount is recorded; the company has not said it will. The other open items are which Aurora units the reservation serves, whether Oklo pays anything before delivery, and when USFR breaks ground in Hertford County.