SB Energy's PORTS-Pike Campus: 9.2 GW of Gas for a 10 GW OpenAI Site

SB Energy's PORTS-Pike campus in Ohio pairs a 10 GW data center leased to OpenAI with 9.2 GW of grid-connected gas. SoftBank took a $3.73 billion equipment loss, and the federal review targets Jan. 29, 2027.

Nuclear & Microgrids Desk

5 min read

Follows SoftBank Posts $7 Billion Q2 Loss on $3.7 Billion U.S. Data Center Charge

Rendering of the planned PORTS-Pike Technology Campus data center buildings beside existing facilities at the former Portsmouth site in Pike County, Ohio

Rendering of the planned data center at the PORTS-Pike Technology Campus, as published by SB Energy.

Rendering: SB Energy

Source · Rendering from the SB Energy PORTS-Pike campus site, used for news reporting.

SB Energy's PORTS-Pike Technology Campus in Pike County, Ohio, is planned as a 10 GW data center fed by a planned 10 GW of new generation, 9.2 GW of it natural gas, and SB Energy says it has signed a 20-year lease with OpenAI. Neither SB Energy nor DOE says whether the data center's 10 GW is IT load or grid demand. Two dated events put it back in view: SoftBank Group's Nov. 10 results, which booked a $3.73 billion loss on power-equipment orders for U.S. AI data centers including this campus, and an ANS Nuclear Newswire report on Nov. 13 that the project's federal environmental review and permitting targets completion by Jan. 29, 2027.

9.2 GW of gas planned for OpenAI's 10 GW PORTS-Pike campus in Ohio
The 10 GW data center campus leased to OpenAI, the 9.2 GW of gas planned to serve it, SoftBank's $3.73 billion loss on equipment orders and the Jan. 29, 2027 review target.

As Voltgrid reported on Nov. 10, SoftBank says its subsidiary revised its equipment procurement strategy "given the evolving requirements of its existing and planned projects," and Reuters, as carried by ANS, reports that the PORTS timeline has not changed. No source read reports the campus cancelled. This file sets out what is planned at the former Portsmouth Gaseous Diffusion Plant site, who pays for it, which approvals are still open and what the targets are.

For OpenAI, the campus is a multi-gigawatt site with its own supply planned beside it. How firm that supply is depends on equipment orders, permits and a transmission build that are not all disclosed. The Department of Energy (DOE) says the new generation will connect to the local grid, so this is grid-connected generation planned for the campus, per DOE, not an islanded supply.

The technology

SB Energy's campus page lists 10 GW of new power capacity, including 9.2 GW of natural gas generation, plus 765 kV transmission lines. DOE's March 20 announcement says the same 9.2 GW of gas is part of 10 GW of new generation that will connect to the local grid and serve the data center. Neither page names a turbine supplier or a model, or the make-up of the 10 GW total beyond the 9.2 GW of gas. Neither source says where the gas plants will stand; ANS, relaying a DOE-EM podcast, says at the site. A microgrid is local generation and controls inside a defined boundary that can run apart from the grid; neither source describes islanding or microgrid controls, so this is grid-connected generation, not a microgrid.

The data center itself is described in the Federal Permitting Dashboard entry, read on Nov. 15: two data center buildings on about 1,300 acres of private land next to DOE's Portsmouth Site, with access roads, administrative buildings, substations, laydown yards and parking. SB Energy's page describes the campus as spanning private and remediated DOE land. The first phase is 800 MW, which SB Energy says starts construction in 2026, with capacity expected online in phases from 2028. The page does not say whether the 800 MW is IT load or grid demand.

The deal and the money

SB Energy says it has signed a 20-year lease with OpenAI, and that NVIDIA will provide credit support and be the exclusive AI compute provider at the campus. The lease terms and price are not disclosed. DOE describes the overall arrangement as a public-private partnership with SoftBank and AEP Ohio, announced with the Department of Commerce on March 20.

The gas generation is tied to the U.S.-Japan Strategic Trade and Investment Agreement. DOE puts the Japanese funding for the 9.2 GW at $33.3 billion; SB Energy's page gives $33 billion and says the new gas generation, funded in part through that agreement, will be owned by the U.S. government; the page says SB Energy funds all of the grid upgrades and transmission. The two parties give different transmission figures: DOE says SB Energy is investing $4.2 billion with AEP Ohio to upgrade and build lines in Southern Ohio, while SB Energy's page lists a $5.1 billion grid investment through AEP Ohio. DOE says SB Energy has committed to make excess transmission and generation capacity available to the grid.

SoftBank's own financial report, for the six months to Sept. 30, says its subsidiary Silver Bands 7 signed capacity reservations and purchase contracts for power-generation equipment for U.S. AI data center projects, including PORTS-Pike. Its payments since the previous fiscal year reached $9.48 billion. After revising its procurement strategy, SoftBank recognized a $3.73 billion loss: $2.85 billion on non-refundable advance payments and $0.88 billion on contract changes and settlements. Silver Bands 7 may receive rebates of up to $2.1 billion over 10 years on future purchases, which SoftBank has not booked as an asset. The report does not split the loss by project. The Financial Times reported on Nov. 10, citing sources and as carried by ANS, that $3.7 billion of the loss came from non-refundable down payments on gas turbine equipment for this campus. SoftBank's own report names several projects, does not mention gas turbines and splits the charge into advances and settlements, so the two accounts differ.

Licensing and timeline

The campus is a FAST-41 covered project, the federal process for setting and publishing permit timetables; its Federal Permitting Dashboard entry was posted on June 11, 2026, with the U.S. Army Corps of Engineers as lead agency. The dashboard shows the review in progress, two of four processes completed, and an estimated completion date of Jan. 29, 2027. The Fish and Wildlife Service also has actions to take. On Sept. 28, 2026, the Permitting Council's executive director granted the Corps an extension of the completion dates for the environmental assessment and the permit decision under Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act.

Four dated steps are done; the Jan. 29, 2027 review estimate and 2028 first capacity are still ahead.

Graphic: Voltgrid News

That FAST-41 entry covers the data center complex. The dashboard description does not cover the gas plants, and no air permit for them was found in the sources read. ANS reports, citing Reuters, that the development timeline has not changed. The groundbreaking was held on March 20, according to a DOE photo caption carried by ANS.

What it means for data centers

A 10 GW campus with 9.2 GW of planned gas generation puts the project's schedule on turbines and transmission, not on a utility's queue alone. SoftBank's report shows the cost of locking in equipment early and then changing plans: $2.85 billion in non-refundable advances, against rebates of up to $2.1 billion that depend on future purchases and other conditions. Local opposition is also on the record: ANS, citing Ballotpedia, reports that Ohio voters approved eight local measures on Nov. 3 banning data centers at or above a certain power level. The campus was not on any ballot, ANS reports.

What to watch

The next dated step is the dashboard's estimated completion of environmental review and permitting on Jan. 29, 2027; the Permitting Council extended the Corps' completion dates for the environmental assessment and permit decision on Sept. 28. SB Energy targets construction of the first 800 MW phase in 2026 and first capacity in 2028. Still undisclosed are the turbine supplier and model, the gas supply and pipeline, the air permits, the make-up of the 10 GW total beyond the gas, and how much of SoftBank's $3.73 billion loss relates to this campus in the company's own accounts.