TRISO-X TX-1 Fuel Plant: Oak Ridge Factory for the First 11 Xe-100s
X-energy's TRISO-X TX-1 fuel plant is licensed but unfinished, with capacity projected for the first 11 Xe-100s. An NRC weld demonstration is due by Nov. 20; TX-1's cost and start date are undisclosed.
5 min read
Follows TRISO-X Has 30 Days to Prove TX-1 Welds Under NRC Order, No Civil Penalty

Steel framing at the TRISO-X fuel plant, from X-energy's release on the Part 70 licence.
Image: X-energy
Source · Press image from the X-energy newsroom, used for news reporting.
TRISO-X, X-energy's fuel subsidiary, must make available to the Nuclear Regulatory Commission for inspection a demonstration that the braced-frame welds at its TX-1 fuel plant in Oak Ridge, Tennessee, meet its licensed codes. The NRC's confirmatory order of Oct. 21 gives it 30 days from that date, which puts the deadline at Nov. 20.
The order resolves an apparent violation without a civil penalty, and Voltgrid covered its terms on Nov. 16. The plant behind it matters more than the welds. TX-1 is where X-energy plans to make the pebble fuel for its Xe-100 reactors, and the company says it will have capacity for the first 11 of them. X-energy says TX-1 was developed initially to support Dow's Seadrift plant in Texas under a Department of Energy program; it has not said which later projects, including those Amazon backs, TX-1 will supply.
What TRISO Fuel Is and What TX-1 Will Make
TX-1 makes TRISO fuel: grains of uranium coated in layers of carbon and silicon carbide that hold fission products in at very high temperatures, packed into graphite pebbles. The Xe-100 is a helium-cooled, high-temperature gas reactor that runs on those pebbles. The uranium is HALEU, enriched to 15.5% U-235 for steady-state operation, X-energy's filing says, against under 5% in today's fleet.
Once running, TX-1 is expected to turn out about 700,000 pebbles a year, equal to 5 metric tons of uranium, X-energy said on Sept. 24. That is a company projection for a plant that has not yet made commercial fuel. In its third-quarter 10-Q, filed Nov. 12, X-energy says TX-1 will support the first 11 Xe-100 reactors at steady state, and that a second plant on the same site, TX-2, is expected to support fuel for up to 44 reactors a year. TX-2 is planned and not yet built. ANS Nuclear Newswire reported on July 17 that, according to TRISO-X, TX-1, TX-2 and a laboratory plant, TX-L, together would supply enough fuel for approximately 55 Xe-100s, which the company put at about 4.5 GW; that too is a projection.
A fuel plant is a licensed nuclear facility in its own right, and X-energy's filing names its Oak Ridge plants as where TRISO-X fuel will be made. A reactor that gets its permit on time still needs its first core.
DOE Cost Share and TX-1 Funding
X-energy builds and will own TX-1, its 10-Q says. The plant sits inside DOE's Advanced Reactor Demonstration Program (ARDP): a February 2021 agreement split $2.4 billion of eligible costs, as estimated at the initial award, 50/50, for $1.2 billion of reimbursement across the Xe-100 design, TX-1 and Dow's Seadrift plant. The filing says estimated total project costs have risen since 2020. X-energy is eligible for about half of TX-1's cost; later fuel plants are not. Congress has appropriated about $1.1 billion toward the $1.2 billion commitment, and the current ARDP budget period runs from March 2025 to March 2027, with no assurance of more, according to the filing.
The 10-Q does not disclose TX-1's total cost. It says development delays and cost increases have already occurred at the site, from infrastructure and oversight requirements, design changes, supply constraints, procurement delays and environmental analyses. Company-wide, capital spending on facility construction rose $98.8 million in the first nine months of 2026 against a year earlier, offset by a $42.5 million rise in grant reimbursements. X-energy held cash and cash equivalents of $1,044.1 million at Sept. 30. ANS Nuclear Newswire reported in July that TRISO-X had received an $11 million grant from Tennessee's Nuclear Energy Supply Chain Investment Fund.
Amazon's agreements with X-energy reach into the plant's output. The 10-Q says X-energy granted Amazon first-priority allocation of Xe-100 manufacturing queue slots from 2031 to 2039, for Amazon to allocate to the utilities and independent power producers that would own the plants, and must offer it minimum TRISO-X fuel allocations matching its most favored customers. Amazon is not obligated to buy. As Voltgrid reported, the 10-Q also says both Amazon-backed Xe-100 projects depend on Amazon funding, and Amazon's broader Xe-100 pact remains an MOU.
Licensing, Construction Timeline and HALEU Supply
A Part 70 licence governs the uranium that fuel is made from, not a reactor. The NRC issued TRISO-X a 40-year special nuclear material licence under 10 CFR Part 70 on Feb. 13, 2026, for TX-1, and X-energy says it will also cover the planned TX-2. X-energy says TX-1 will be the first Category II fuel facility in the United States. The licence is not permission to start: the NRC still has to run a final inspection of equipment, safety systems, procedures and staff before TRISO-X can receive HALEU and begin operations.
Site preparation began in October 2024, the 10-Q says; ANS Nuclear Newswire's July account dates the start of construction to November 2025. The 214,000-square-foot building's structure was finished on Sept. 24, and Clark Construction Group is now fitting the interior, installing fuel fabrication equipment and building a graphite matrix powder building. Neither the filing nor the releases read for this file give a start date for commercial fuel production.
ARDP agreement
50/50 cost share of $2.4 billion eligible costs at award ($1.2 billion reimbursement); covers Xe-100 design, TX-1 and the Seadrift plant.
Site preparation begins
Per X-energy's 10-Q.
NRC Part 70 licence
40-year special nuclear material licence issued to TRISO-X.
Weld stop-work
TRISO-X stop-work on the x-bracing welds, confirmed by letter Apr. 5.
Vertical construction complete
214,000 sq ft; interior buildout and equipment installation follow.
NRC Confirmatory Order
Modifies licence SNM-7007; no civil penalty.
What to watch
Weld demonstration due
The order gives 30 days from its Oct. 21 issue date to make the demonstration available for NRC inspection.
Further order actions
Items due within three, six and 12 months of the order, plus a status letter every three months.
ARDP budget period ends
Current budget period runs March 2025 to March 2027; no assurance of funding beyond.
Final NRC inspection
Before TRISO-X receives special nuclear material and starts operations. No date given.
Commercial fuel production
No start date in the filing or releases.
The weld order adds deadlines on top. Beyond the 30-day demonstration, it sets further actions due within three, six and 12 months and a status letter every three months. TRISO-X issued a stop-work on the bracing welds on April 3, and the order says ultrasonic tests on all of the braced-frame intersection welds measured at or above 7/16 inch, a revised design that replaced the original 5/8 inch. The order and its Federal Register notice say nothing about TX-1's schedule or cost.
TX-1 can only make fuel from uranium it receives. X-energy says it secured the initial HALEU for its first Xe-100 project, with Dow, through DOE's HALEU Availability Program. For later units, X-energy signed a definitive agreement with Centrus on Aug. 6, 2026 for enrichment at Piketon, Ohio, phased with its pipeline; X-energy says that at full execution it would cover a portion of the initial fuel needs of its 11.5 GW pipeline, not all of it. Centrus's new Piketon capacity targets 2029, though Centrus has not said which customers that capacity serves, and the 10-Q warns that the domestic HALEU industry is still in its early stages.
What TX-1 Means for Amazon's Xe-100 Plans
X-energy says TRISO-X fuel will be made in Oak Ridge, and its Amazon agreements carry minimum fuel allocations, but it has not said which projects TX-1 supplies after Dow's, including Energy Northwest's Cascade project and the AEP study in Indiana that Amazon funds. Dow's Long Mott plant now holds its NRC construction permit, so fuel becomes one of the tests for the first Xe-100s. On X-energy's projection, TX-1 has capacity for the first 11 reactors; the 10-Q expects TX-2, planned on the same site and not yet built, to support up to 44 a year. If TX-1 slips, that would push back the first cores it was built to make.
What to watch
By Nov. 20, TRISO-X's weld demonstration is due to be available for NRC inspection. Next come the order's three-month actions and first quarterly status letter around January 2027, the end of the ARDP budget period in March 2027, the NRC's final pre-operation inspection of TX-1, a funding decision and construction start for TX-2, and Centrus's phased HALEU deliveries.
Sources
- 01TRISO-X Completes Vertical Construction of TX-1 Fuel Fabrication FacilityX-energyx-energy.com
- 02X-energy, Centrus Sign HALEU Supply Agreement for Xe-100 Advanced Small Modular Reactor DevelopmentX-energyx-energy.com
- 03New grant to fund continued construction of TRISO-X fuel facilitiesANS Nuclear Newswireans.org
- 04In the Matter of TRISO-X, LLC; Confirmatory Order Modifying LicenseFederal Register (NRC)public-inspection.federalregister.govas read on Nov 16, 2026
- 05TRISO-X Receives First-Ever Part 70 HALEU Fuel Fabrication LicenseX-energyx-energy.com
- 06X-Energy, Inc. Form 10-Q for the quarter ended September 30, 2026X-energy (SEC 10-Q)sec.gov
- Published
- Sources
- 6 cited