VoltgridNews

Amazon Wheatfield Data Center: AWS Held $7B Groundbreaking on Nov. 12

Amazon's $7 billion Project Rise campus in Wheatfield, Indiana covers 304 acres next to NIPSCO's Schahfer plant. Gas and battery supply of up to 2.6 GW plus 400 MW was planned; building count and IT load are unreported.

Chips & Power Desk

3 min read

Server racks and cabling in an Amazon Web Services data center hall, with a worker blurred in motion

An AWS data center interior from Amazon's November 2025 Northern Indiana announcement page; it is not a picture of the Wheatfield site.

Image: Amazon

Source · Press image from the Amazon newsroom, used for news reporting.

Amazon Web Services (AWS) held a ceremonial groundbreaking on Nov. 12, 2026, for its Wheatfield data center, Project Rise, a planned $7 billion campus on 304 acres in Jasper County, Indiana, according to Inside Indiana Business.

The site is on land owned by the utility NIPSCO, near NIPSCO's R.M. Schahfer Generating Station, as Northwest Indiana Business Magazine reported when Jasper County approved the project in June 2026. Inside Indiana Business said more than 350 workers were already on site, and that the county's development agreements commit Amazon to $98 million up front, $23 million a year for the next decade and $25 million to extend water service in Wheatfield Township. Amazon will also build the water and wastewater infrastructure the campus needs.

Why it matters for power

A campus on a power plant site ties the build to the gas and battery supply NIPSCO's affiliate NIPSCO Generation (GenCo) is planning for Amazon. Utility Dive reported on Nov. 25, 2025, that GenCo planned 2.6 GW of gas generation from two 1.3 GW plants plus a 400 MW, four-hour battery, for about $7 billion including transmission. Deliveries were to start by Jan. 1, 2027 and reach 2.4 GW by the end of 2032. NiSource has since said, in its Oct. 28, 2026 quarterly filing, that the gas plant is now expected to start commercial operation in 2030, as Voltgrid reported. That energy figure is separate from the $7 billion campus cost, and neither source breaks the campus load into buildings or megawatts.

As reported Nov. 25, 2025, GenCo planned deliveries to Amazon to start by Jan. 1, 2027 and reach 2.4 GW by the end of 2032.

Graphic: Voltgrid News

Utility Dive also said the framework is meant to keep existing customers from paying for infrastructure built for Amazon, and that Amazon holds a one-time option, by March 31, 2029, to cut its contracted capacity by 1,200 MW. Separately, according to testimony to Indiana's Office of Utility Consumer Counselor cited by Northwest Indiana Business Magazine, NIPSCO is building a 400 MW gas peaker plant at the site, with construction and financing costs of $643.7 million.

Site, Jobs, Cooling and Amazon's Indiana Plans

Northwest Indiana Business Magazine said the campus is expected to create 250 jobs. It said county property tax revenue from the parcel, now about $70,000 a year, is to rise to more than $20 million a year over 10 years. The magazine said the buildings will mostly use outside air for cooling and rely on water-based cooling about 2% of the year, on very hot days. Amazon will also restore 425 acres of habitat in the Kankakee River watershed with the Shirley Heinze Land Trust, the magazine said.

Inside Indiana Business described Wheatfield as part of a $15 billion northern Indiana investment and a $33 billion data center investment statewide. The same report said Amazon has invested $11 billion in New Carlisle in St. Joseph County, and that the $15 billion was announced in November 2025 for new northern Indiana campuses, including one in Hobart. Northwest Indiana Business Magazine, writing in June, cited only the $15 billion northern Indiana commitment, so the statewide total rests on one outlet.

What is not confirmed yet

The sources read give no building count, no critical IT load in megawatts and no opening date for Wheatfield. Other reports of the groundbreaking cite a different number of buildings and a different power figure; those were not confirmed here. The Utility Dive power figures date from November 2025, and the current state of the state and federal approvals for the Amazon contract was not confirmed in the pages read. The full NWI Times account of the ceremony was behind a paywall and was not used.

Sources

Published
Sources
3 cited