Alpiq Files for 300 MW / 1,200 MWh Niedergösgen Battery in Switzerland
Alpiq has applied to Switzerland's ESTI for a 300 MW battery with more than 1.2 GWh at Niedergösgen; commissioning is planned for 2029, but no approval has been granted.
2 min read

Alpiq's visualisation of the planned 300 MW battery on its land in Grossacker, Niedergösgen, between the Gösgen hydropower plant and the Old Aare. It is an illustration of the plan, not a photo of a built site.
Image: Alpiq
Source · Press image from the Alpiq newsroom, used for news reporting.
Alpiq announced on Nov. 26, 2026, that it has submitted a planning approval application to Switzerland's Federal Inspectorate for Heavy Current Installations (ESTI) for a 300 MW battery with more than 1.2 GWh of storage at Niedergösgen.
The battery energy storage system (BESS) would stand on Alpiq-owned land in the Grossacker area of Niedergösgen, in the canton of Solothurn, between the company's Gösgen hydropower plant and the Old Aare river, according to Alpiq's media release. ESTI is the authority that grants the approval, and a public consultation follows the start of the procedure. The Swiss news agency Keystone-SDA, as published by Nau.ch, reported the same figures and counted 288 battery containers.
300 MW against 1,200 MWh works out to four hours of full-power discharge, a duration that Alpiq's own release frames as supplying around 500,000 households for more than four hours when fully charged. Alpiq calls that a theoretical figure. For Switzerland's transmission grid, the draw is the siting: Alpiq points to the proximity to existing energy infrastructure, including the Gösgen nuclear and hydropower plants, and to a major grid connection point.
What Alpiq has planned for the site
The plans provide for 72 groups of four battery containers each, together with the power conversion and grid connection equipment, Alpiq said. Alpiq's release names no battery supplier, cell chemistry or container vendor. Construction and design are to be coordinated with a neighbouring project for a new fish pass.
Alpiq reached a first milestone in June 2026, when an agreement in principle with Swissgrid, the national transmission system operator, secured 300 MW of connection capacity. Its June 30 release described that step as a pre-connection agreement. Construction is scheduled to begin in 2027, subject to the necessary approvals, with commissioning planned for 2029. An information event for Niedergösgen residents is set for mid-January 2027.
Commissioning is planned for 2029; construction in 2027 is scheduled subject to approvals, and no ESTI decision date has been published.
Graphic: Voltgrid News
How it fits Alpiq's storage push and the European market
Alpiq said in June that it has secured a battery portfolio of more than 1 GW across several European markets, of which 130 MW is operating and 230 MW is under construction. Niedergösgen is the first large-scale battery Alpiq has planned in Switzerland, which Alpiq says would be among the largest in the country.
For scale, Voltgrid reported that Saxony approved a 700 MW / 2,800 MWh battery at Oberschöna in Germany on a similar four-hour design, and that EDF bought a 250 MW / 1 GWh project in New South Wales. Niedergösgen sits between the two in power. Unlike Oberschöna, it has only reached the filing stage.
What is not confirmed yet
No approval has been granted. ESTI has not published a decision date, and the public consultation and any objections are still ahead. Alpiq's release does not give the project's cost, its battery supplier, its cell chemistry or how it will earn revenue, and it describes the 2027 construction start as subject to approvals.
Sources