Anthropic Queensland Data Centre: Shell Unit Objects to 1.4 GW Campus

Shell unit QGC asked Western Downs council to hold the 1.4 GW Anthropic-leased campus until gas operations are protected, Capital Brief reported, after a Nov. 24 federal environmental clearance.

Chips & Power Desk

3 min read

Aerial view of the planned Western Downs Digital Park data centre campus near Braemar, Queensland, as shown on the developer's project page

Developer's visual of the Western Downs Digital Park site in Queensland, which Zerra DC plans at 1.44 GW across up to four phases.

Image: Zerra DC / Western Downs Digital Park

Source · Press image from the Western Downs Digital Park project page, used for news reporting.

Shell's Queensland Gas Corporation (QGC) has asked Western Downs Regional Council not to approve the 1.4 GW data centre campus leased to Anthropic until the developer guarantees it will not affect gas operations, Capital Brief reported on Nov. 27.

Capital Brief's report came three days after Australia's National Environmental Protection Agency decided on Nov. 24 that the Western Downs Digital Park needs no assessment under the Environment Protection and Biodiversity Conservation (EPBC) Act, according to Mingtiandi, which cited the notice on the federal approvals portal. The agency found the project "unlikely to have a significant impact on matters of national environmental significance", ABC News reported on Nov. 26. QGC said it is "willing to work constructively" with developer Zerra DC, the council and government agencies, and Shell said it is not generally opposed to data centres, Capital Brief reported.

The federal step removes one gate but not the ones that decide whether the site is built. The council is still assessing the development application, public submissions closed on Nov. 11, and state approval is also outstanding. Anthropic's lease of the first stage remains subject to Foreign Investment Review Board approval, Mingtiandi reported. The site sits near the Braemar substation in a region the developer describes as holding about 5.4 GW of generation and storage capacity, so a gas producer's objection is a conflict over land use inside an energy precinct, not a remote-site dispute.

The federal EPBC step was cleared Nov. 24; council, state and FIRB decisions are still outstanding for the 1.44 GW campus (developer claim).

Graphic: Voltgrid News

Capacity, power and water

Mingtiandi and the developer's project page put the campus at 1.44 GW across up to four phases; Capital Brief rounds it to 1.4 GW. None of the pages we read says whether that figure is critical IT load, utility interconnection or total campus demand, so it should not be read as IT capacity. Zerra DC says the site will draw electricity from the national electricity market, with Powerlink and the Queensland government, and that it will bear the full cost of its grid connection. Phase 1 includes an on-site battery-backed power conditioning system and a substation.

On water, Zerra DC says the halls will be 100% air-cooled with no evaporative cooling, and models 21 kL a day for the first building, of which 13 kL is remaining raw-water demand and 8 kL is recycled on site. Construction water is proposed to come mainly from processed water from nearby gas operations, which is the sector QGC works in. Those are developer modelling figures, not council-verified numbers, and the developer says they may change as design is refined. Mingtiandi noted that the EPBC referral did not address power demand, water use or emissions.

Context and cost

The headline cost differs by source. ABC and Capital Brief give A$32 billion; Mingtiandi gives A$14.5 billion (US$10.4 billion) for the project, and we could not reconcile the two. Opposition is broad: Mingtiandi counted 757 documents on the council portal, mostly objections, and a state e-petition with 24,738 signatures. Capital Brief said nearly 600 objections were filed and that QGC's was not a template from activist groups.

Anthropic's Australian subsidiary agreed in September to lease the first stage, with the consortium including Zerra DC, Macquarie Capital and Dexus-controlled Australian Data Centres. It is one of several sites Anthropic is tied to, after the TeraWulf Kentucky lease with a Google backstop and talks over an Edmonton campus with a 920 MW gas plant, as Voltgrid reported. Community pushback has also hit other Australian projects, as in the 350 MW Mulwala proposal Voltgrid covered on Nov. 23.

What is not confirmed yet

The date QGC lodged its submission is not stated by Capital Brief, and we could not read the submission itself, so its exact terms are unconfirmed. We read the federal notice only through Mingtiandi's account and ABC's report, not the portal entry. No council decision has been reported. Any start date depends on council and state approvals and on the Foreign Investment Review Board.