Galaxy Digital Registers $1.3B, 349,594 sq ft Helios 5 Building in Texas
Galaxy Helios II LLC registered Helios 5 in Dickens County on Nov. 23: 349,594 sq ft, $1.3B, due June 2028. Galaxy's filings show 526 MW of CoreWeave critical IT across three phases.
2 min read

Galaxy's rendering of the Helios data center campus in Dickens County, Texas. It is a company illustration, not a photo of the Helios 5 building.
Image: Galaxy
Source · Press image from the Galaxy website, used for news reporting.
Galaxy Digital's Helios II LLC registered a $1.3 billion, 349,594 sq ft data center building, Helios 5, with Texas regulators on Nov. 23, 2026, according to the state's TABS record; DatacenterDynamics reported it on Nov. 27.
The Texas Department of Licensing and Regulation (TDLR) record, TABS2027006560, covers a one-story data center and office building at 1003 FM 193 in Afton, Dickens County. It lists a Nov. 2, 2026 start and a June 21, 2028 completion date. The project is privately funded, its status is "Project Registered", and no tenant is assigned on the form. DatacenterDynamics, which puts the building in Phase III of the campus, rounds the floor area to 349,595 sq ft.
What it means for power and capacity
The filing gives no megawatt figure, so the building's load is unknown. Galaxy's own third-quarter 2026 materials, filed with the SEC on Oct. 27, set out how CoreWeave's lease is split: 133 MW of contracted critical IT load in Phase I, 260 MW in Phase II and 133 MW in Phase III, 526 MW in all. Those figures are IT load, not utility power. The same filing puts gross power capacity at 800 MW, about 200 MW for Phase I, 400 MW for Phase II and 200 MW for Phase III. Phase III rent is due to start in 2028, and the new building's registered completion falls in June 2028.
Neither document says Helios 5 is the Phase III lease, so Voltgrid does not tie the building to a lease figure. The TDLR project name is "Galaxy Helios Phase 3", and the Phase III label also comes from DatacenterDynamics.
Where the campus stands
By Galaxy's account, all 133 MW of Phase I was delivered to CoreWeave by the end of the second quarter, and Phase II's two buildings and substation are under construction, with data hall deliveries scheduled to begin in the second quarter of 2027. The campus has 1,630 MW of approved power, with a path to more than 3,600 MW, and Galaxy says 830 MW of approved capacity is not yet leased and that it is in talks with prospective tenants. Galaxy says CoreWeave's lease runs a 15-year base term.
Galaxy's earlier TDLR filings, all registered March 13, 2026, show how the build is stacking up. Helios 2 is 199,124 sq ft at $900 million, and Helios 3 and Helios 4 are each 349,594 sq ft at $1.3 billion. Adding Helios 5, the four registrations total 1,247,906 sq ft and $4.8 billion, by Voltgrid's arithmetic, with completion dates running from February 2027 to June 2028. These are estimated costs on state registration forms, not Galaxy's capital budget.
Helios 5 matches Helios 3 and 4 at 349,594 sq ft and an estimated $1.3B; Helios 2 is 199,124 sq ft at $900M, per TDLR registrations.
Graphic: Voltgrid News
For comparison, Voltgrid reported that Core Scientific filed a $1.3 billion Hunt County, Texas data center at 285 MW in mid-November.
What is not confirmed yet
The Galaxy materials read for this report do not mention the registration. It is not stated which lease phase, if any, covers Helios 5, how many megawatts it will draw, or whether CoreWeave or a new tenant will occupy it. The TDLR record is a registration, not a construction permit, and the cost is an estimate. Because the registration is dated Nov. 23, this report runs four days after it was filed.
Sources
- 01Galaxy Digital files for next phase of development at Helios data center campus in TexasDatacenterDynamicsdatacenterdynamics.com
- 02Galaxy Helios Phase 3, Helios 5: TDLR TABS project TABS2027006560Texas Department of Licensing and Regulationtdlr.texas.gov
- 03Galaxy Digital third-quarter 2026 overview: Helios and the CoreWeave leaseGalaxy Digital (SEC filing)sec.gov