Drax Data Centre Consultation Ends Dec 3; Phase 1 Imports Grid Power
The Drax data centre consultation closes Dec. 3 on a phase 1 targeting up to 100 MW from early 2028 on grid power; phase 2's behind-the-meter ambition needs a PPA and consent.
4 min read
Follows Drax Data Centre Plan: Brookfield Sees £20bn+, Up to 100 MW From 2028

Drax Power Station in North Yorkshire, where Drax, Brookfield and Radiant plan a data centre campus.
Image: Drax
Source · Press image from the Drax website, used for news reporting.
The Drax data centre consultation on phase 1 of the AI campus at Drax Power Station closes on Dec. 3, 2026, a month after Drax, Brookfield and Radiant set a target of up to 100 MW of compute capacity by early 2028.
As Voltgrid reported on Nov. 3, Brookfield estimates total potential investment, including semiconductor chips, could exceed £20 billion, with an initial £2.5 billion as part of phase 1. That story covered the announcement. This file sets out how the campus would get its power at each phase, what is binding, and what is still missing before anything is built.
The supply is not new generation, not nuclear and not a microgrid. In phase 1, the data centre would use existing infrastructure to import power directly from the grid, managed by Drax, according to Drax's stock-exchange announcement. Phase 2 is expected to use existing Drax generation, which burns compressed wood pellets, behind the meter under a long-term power purchase agreement (PPA), subject to the necessary consents. No tenant has been named, no power-supply contract has been signed, and no final investment decision has been taken.
The site and the power
Drax says the estate covers more than 1,000 acres, has about 4 GW of grid access and 2.6 GW of active dispatchable generation with its cooling systems, and sits next to one of the country's largest substations. Chief executive Will Gardiner said it is one of few UK sites able to supply large-scale reliable power directly to data centre customers from existing and underused generation.
The one idea that matters is that Drax uses megawatts in three different ways, and they should not be added together. The site figures above describe the station's grid connection and generation. The data centre phases are sized as capacity: up to 100 MW of compute capacity in phase 1 and an ambition for 500 MW in phase 2. Drax does not say whether the 100 MW is IT load or grid draw, so how much power each phase would take is not yet known. Drax describes phase 2 as a behind-the-meter energy solution delivering power around the clock directly to a data centre.
The third figure sits in the station's subsidy contract. Drax signed a Contract for Difference (CfD) with the UK government in November 2025 for about 6 TWh a year of biomass generation from April 2027 to March 2031, which Drax says is about 30% of the annual baseload output of its 2.6 GW. The CfD includes a mechanism for Drax to request up to 500 MW of generating capacity to power a data centre in that period, which the government and the Low Carbon Contracts Company must agree, weighing value for money for consumers, energy security and sustainability, the company said. That 500 MW is a cap on generation Drax may divert, not the size of a data centre. Drax does not say that phase 2 depends on this mechanism; in our reading, the two overlap until March 2031. The Register wrote that it could allow AI servers to run on electricity from burning imported wood pellets.
The deal and the money
The parties describe a strategic partnership, not a supply contract. Radiant, Brookfield's UK-headquartered AI infrastructure platform, leads design, customer engagement and commercialisation, and wants anchor customer commitments before construction starts. Drax leads land, power integration and planning. The Brookfield-Qai AI infrastructure joint venture, with Qatar's Qai, provides the backing. The £20 billion figure is Brookfield's estimate, and The Register called it more ambition than money on the table.
For phase 2, Drax's release gives an ambition to ramp up to 500 MW of capacity between 2028 and 2031, while the stock-exchange announcement speaks of an ambition to develop options for 500 MW of data centre capacity in that window. Neither is a commitment. Phase 3 is an ambition for more capacity after 2031 on the same behind-the-meter model, and Drax's only figure for the whole project is more than 1 GW. Drax has not said how much power the campus would draw from the grid at each step.
Done steps are filled; phase dates are Drax targets and ambitions, and phase 2 needs a PPA and consents.
Graphic: Voltgrid News
Planning and timeline
The consultation opened on Nov. 4, with drop-in events at Drax Village Hall on Nov. 19 and 20, YorkMix reported. Drax will use the feedback for a full planning application to North Yorkshire Council, which it is targeting for submission later this year, according to YorkMix. The draft masterplan places the site off the A645 at the south end of the station, with a data hall and a tallest structure of about 27 m.
Beyond planning, Drax lists regulatory and network approvals from the government and the relevant agencies, an acceptable tenant, commercial agreements and a final investment decision by each party as conditions for phase 1. The Q1 2028 date is a target set against all of them.
What it means for UK data centres
If built in full, the project could become one of the largest data centres in the UK, the partners said. For scale, The Register cited a government estimate that all of Britain's existing data centres use around 2 GW of electricity, a measure of power use rather than compute capacity. The bigger test is phase 2: it is the step that turns a grid-connected campus into one fed directly by a power station, and it needs a PPA and the necessary consents while the CfD runs to March 2031.
What to watch
The consultation closes on Dec. 3, 2026, and Drax is targeting the planning application later this year. Still undisclosed are the tenant, the price and terms of any power supply, the timing of network approval, and whether the government and the Low Carbon Contracts Company will allow up to 500 MW of CfD-backed generation to serve a data centre. The CfD period starts in April 2027, ahead of the phase 1 target.
Sources
- 01Drax reveals AI data centre deal worth up to £20bn – Residents urged to have their sayYorkMixyorkmix.com
- 02Drax, Brookfield and Radiant announce £20bn partnership to deliver GW-scale data centre capacity at Drax Power StationDrax Groupdrax.com
- 03Drax wants to feed Britain's AI habit with £20B datacenter at biomass power stationThe Registertheregister.com
- 04Strategic partnership for GW-scale data centre (RNS)Drax Groupdrax.com
- Published
- Sources
- 4 cited