NYPA's Upstate Nuclear Project: At Least 1 GW, No Partner Chosen Yet
NYPA's nuclear project upstate, at least 1 GW, has 10 qualified firms on large-reactor and SMR pathways but no site, design, partner or cost disclosed and no NRC filing reported. The RFQ asks for a path to start construction before 2033.
4 min read
Follows NYPA Qualifies 10 Nuclear Developers for At Least 1 GW Upstate Plan

Gov. Kathy Hochul at the Advanced Nuclear NY Summit, where the state's nuclear Master Plan was introduced on Nov. 18, 2026. The photo shows the event, not the NYPA project site.
Image: Office of Governor Kathy Hochul
Source · Press image from the Office of Governor Kathy Hochul, used for news reporting.
The New York Power Authority (NYPA) qualified 10 developers on Nov. 12, 2026 for its nuclear project to build at least 1 GW upstate, and on Nov. 18 Gov. Kathy Hochul introduced the state's Master Plan for 5 GW of new nuclear.
Both events drew short news stories here: the qualification and the Master Plan's 5 GW target. This file is the reference on the project itself. In plain terms, New York's state power authority has a shortlist and a target, not a plant. No site, reactor design, partner, price or buyer has been chosen, and no licence application has been reported. NYPA calls the project a critical early component of the state's 5 GW goal that will contribute to an 8.4 GW nuclear backbone.
What Reactors NYPA's Qualified Firms Could Build
NYPA's request for qualifications (RFQ) offered two technology pathways: large-scale reactors (LSR) and small modular reactors (SMR). According to ANS Nuclear Newswire's June 4 report on the RFQ, the document cited large reactors "such as the AP1000" and SMRs "such as the BWRX-300" as examples, not as choices. Six firms qualified for both pathways: Avangrid, Elementl Power, NextEra Energy, Oppenheimer Energy, The Nuclear Company and Turquoise Power. Four qualified for SMRs only: Blue Energy, Holtec International, TerraPower and X-energy.
NYPA did not say which design each firm put forward. The SMR-only firms' own pages describe what they sell. X-energy says its Xe-100 is a helium-cooled, high-temperature reactor on TRISO-X pebble fuel, designed to produce 80 MWe, or 200 MWt of heat, per module, and says a four-pack gives 320 MWe. TerraPower describes Natrium as a 345-megawatt sodium fast reactor paired with molten-salt energy storage; the NRC lists it at 345 MWe per unit. Holtec says its SMR-300 is designed and manufactured at its Camden, New Jersey campus, says each unit is designed to generate about 340 MWe, and says it can run in island mode during grid outages to power large loads connected directly to the plant. No SMR-300 has been built yet. Blue Energy's Texas project is set out in our Port of Victoria file; NYPA has not said what Blue Energy offered it.
The one idea that matters is scale. A reactor's electric rating decides how many units a 1 GW plant needs. Westinghouse lists its AP1000, the large design the RFQ names as an example, at a nominal 1,150 MWe net per unit, so one unit would clear the floor. An SMR plant reaches 1 GW only as a group of modules. NYPA asks for at least 1 GW, not a unit count, and has not said which route it prefers. Keep heat and electricity apart: 200 MWt is the heat an Xe-100 module makes, not a 200 MW power plant.
Who pays, and what is binding
NYPA is public power: the country's largest state public power organization, with 17 generating plants and more than 1,550 circuit-miles of transmission. It says it pays for its operations through bond sales and revenue that comes mostly from selling electricity. It has disclosed no cost, financing plan or offtaker for the nuclear project. The RFQ asked applicants for cost assumptions, ownership structures and partnership models, ANS reported.
Nothing here is binding. NYPA says the qualified firms will be invited to later solicitations "as opportunities arise". A qualification is not a selection, a contract or an award. The only dollar figure in NYPA's release is the $10 million of workforce-training funding it says it has awarded. The state's estimate of public support for the full 5 GW is in our Master Plan story.
NRC Licensing and Timeline
No application to the Nuclear Regulatory Commission (NRC), and no pre-application filing, has been reported for the project. The first step comes before any licence: NYPA has to pick a host community, a technology and a development partner. It is targeting that choice "in the coming months" and has given no date. Eight communities have said they want to host a plant. Only after a site and design are settled can a developer seek a construction permit or a combined licence.
The firmest date is a condition, not a schedule. The RFQ requires a credible path to start construction before 2033, so the project stays eligible for the Inflation Reduction Act's investment tax credit, ANS reported. NYPA has not set a target for first power. Separately, the Department of Energy awarded Constellation SMR Development $17.3 million this spring to pursue an NRC early site permit for a future SMR site in New York, ANS reported; Constellation is not among the ten qualified firms.
Three steps are done; the partner pick is a NYPA target with no date, and construction before 2033 is an RFQ condition, not a schedule.
Graphic: Voltgrid News
What it means for New York's large loads
Neither NYPA's release nor ANS's account of the Master Plan ties the project to data centers or names a buyer. NYPA presents it as firm supply for grid reliability while the state electrifies. The grid-shortfall and data-center demand figures behind the plan, and the state's caution about building nuclear for data centers, are set out in our Master Plan story. Until NYPA picks a site and a partner, the project adds no firm megawatts that a large-load developer in New York can plan around.
What to watch
On Jan. 13, 2027, the New York State Energy Research and Development Authority (NYSERDA) holds a public webinar on the Master Plan, ANS reported. In the coming months, NYPA targets naming a host community, technology and partner. That pick shows whether New York goes for a large reactor or a fleet of SMRs, and which firm leads. Next would come an NRC pre-application, then a permit filing. The deadline that frames all of it is a construction start before 2033.
Sources
- 01New York’s 5-GW nuclear master planANS · Nuclear Newswireans.org
- 02New York Power Authority Announces Significant Step in Effort to Deliver at Least 1 GW of Advanced Nuclear EnergyAmerican Public Power Associationpublicpower.org
- 03New York Power Authority Announces Significant Step in Effort to Deliver at Least 1 GW of Advanced Nuclear Energy in Upstate New YorkNew York Power Authoritynypa.gov
- 04New York opens RFQ, RFA windows for nuclear development and workforceANS Nuclear Newswireans.org
- Published