New York Nuclear Master Plan: 5 GW Target, No Timeline or Total Cost
New York's nuclear master plan targets 5 GW of new capacity on top of 3.4 GW, but a state paper puts public support at $15.4-$23.9 billion and NYISO sees a 2033 shortfall.
3 min read
Follows NYPA Qualifies 10 Nuclear Developers for At Least 1 GW Upstate Plan

Gov. Kathy Hochul at the Advanced Nuclear NY Summit, where the state's nuclear master plan was announced.
Image: Office of Governor Kathy Hochul
Source · Official photo from the Office of Governor Kathy Hochul, used for news reporting.
New York's nuclear master plan, the Master Plan for Responsible Advanced Nuclear Development that Gov. Kathy Hochul released on Nov. 18, 2026, is a 30-point roadmap for 5 GW of new nuclear capacity on top of the 3.4 GW the state already has, but the governor's release names no schedule and no total cost.
The plan was co-authored by the New York State Energy Research and Development Authority (NYSERDA) and the Department of Public Service (DPS) and unveiled at the state's third nuclear summit in Rochester, according to the governor's office. It rests on 12 studies and more than 1,000 pages of research, and it supports the Nuclear Reliability Backbone that Hochul ordered in her 2026 State of the State, which the state frames as an 8.4 GW fleet. The release says the plan sets out state actions on commercial viability, siting, community partnerships, regulatory review, workforce and supply chain. ANS Nuclear Newswire, which reported it on Nov. 20, notes that the plan repeatedly cites the one confirmed new project in the state, the Westinghouse eVinci microreactor at Fort Drum.
The plan is a framework, not a build order. Its focus areas include state action on cost reductions, a supplier readiness program, a process to identify host communities and evaluate sites including brownfields, and a review of state regulatory processes. The 13WHAM station in Rochester quoted Hochul on Nov. 18 saying there is no timeline and that the state is still waiting for the federal government to engage.
This follows the New York Power Authority's step on Nov. 12, when it qualified 10 developers for its effort to build at least 1 GW upstate, as Voltgrid reported on Nov. 16. NYPA also received 23 responses from developers and partners, and eight communities and entities answered its siting request, according to 13WHAM.
Who pays
On the same day DPS issued a white paper for the Public Service Commission (PSC), which has not ruled on it. Per FingerLakes1.com, the paper recommends a revenue support mechanism with eligibility rules and a competitive process, and examines state equity and partial protection against construction cost overruns. Multiple Intervenors opposed guaranteeing overruns, and National Grid argued customers should not become the default backstop for delays or cancelled projects.
The only cost figure in the record comes from the June 12, 2026 options paper by NYSERDA and DPS staff: public support programs for 5 GW could total $15.4 billion to $23.9 billion over the first 25 years of operation, in a base case with greenfield sites. The paper says policy variants could cut that range by up to 29%, and use of existing or brownfield sites by up to 19% more. FingerLakes1.com reports the estimates are present-value 2025 dollars and are neither approved subsidies nor total construction costs. At the Rochester summit, Nuclear Information and Resource Service director Tim Judson told 13WHAM that the plan would lead to rate hikes for decades.
What it means for supply and data centers
The timing is the tension. FingerLakes1.com reports that the New York Independent System Operator (NYISO) projects a statewide deficiency of about 225 MW in 2033, rising past 1,850 MW by 2036, while state cost modeling assumes first reactors in commercial operation in 2039, an assumption and not an announced opening. The same report cites about 2,700 MW of added large industrial and data-center demand by 2036, and a sensitivity in which flexible data-center load cuts the 2036 gap to about 850 MW.
The state's modeling assumes first reactors in 2039, after NYISO's projected 2033 and 2036 deficiencies.
Graphic: Voltgrid News
The options paper is cautious about data centers as buyers. It says New York has not pursued data-center expansion as a priority, and that nuclear output dedicated to new data-center load would not meaningfully serve existing system load. It adds that hyperscalers may be the only buyers willing to pay more for new nuclear, yet fit state objectives less well. Voltgrid News has also tracked Big Tech's nuclear power deals.
What happens next
NYSERDA will hold a public webinar on the plan on Jan. 13, 2027 at 12:00 p.m. ET. The PSC still has to consider the white paper's proposals in the Nuclear Reliability Backbone proceeding, and NYPA's choice of host community, technology and partner has no date. The release gives no total cost for the plan itself, so the figure to watch is whatever the PSC adopts for support.
Sources
- 01New York’s nuclear plan faces a timing gap as Upstate power demand growsFingerLakes1.comfingerlakes1.com
- 02New York’s 5-GW nuclear master planANS · Nuclear Newswireans.org
- 03Governor Hochul Announces Completion of Comprehensive Advanced Nuclear Master PlanOffice of Governor Kathy Hochulgovernor.ny.gov
- 04New York Advanced Nuclear Policy Options Paper (NYSERDA and DPS Staff)NYSERDA and NYS Department of Public Servicenews10.com
- 05Hochul unveils plan to add 5 gigawatts of advanced nuclear power in New York state13WHAM13wham.com
- Published
- Sources
- 5 cited