Fermi America Draft EIS: Water District Asks NRC for Data Before Nov. 23

Texas's Panhandle groundwater district approved comments on Nov. 19 asking the NRC for water-demand, well and monitoring data on Fermi America's draft EIS. Comments close Nov. 23; no licence decision yet.

Chips & Power Desk

3 min read

Follows Fermi's Project Matador: Non-Binding 600 MW LOI, AP1000 Target Now 2034

Fermi America rendering of the planned Project Matador campus in Amarillo, Texas, with solar-covered buildings and a power plant on open prairie

Rendering of Fermi America's planned Project Matador campus near Amarillo, Texas. It is an artist's rendering, not a photograph of the site.

Image: Fermi America

Source · Press image from the Fermi America website, used for news reporting.

Texas's Panhandle Groundwater Conservation District approved comments on Nov. 19 asking the NRC for more water data on Fermi America's draft environmental impact statement (EIS) for four planned AP1000 reactors at Project Matador, the Amarillo Tribune reported.

The district's hydrogeologist and programs manager, Ashley Ausbrooks, told the board that the draft EIS generally finds the project's effects on groundwater and surface water will be small, according to the Tribune. She said that conclusion relies partly on the expectation that the project gets its water from the City of Amarillo rather than from groundwater at the site. The comments ask for current groundwater and surface-water demand, more on existing groundwater conditions and wells, how development and drainage could affect groundwater, and how groundwater will be monitored for contamination. Ausbrooks said the district is not claiming the project will harm groundwater; it wants enough data and updated analysis to support the draft's conclusions.

The Nuclear Regulatory Commission (NRC) is accepting public comments until Nov. 23; it says it can ensure consideration only of comments received by then, and will consider later ones if practical. Comments go to docket NRC-2026-0100.

The comments add water to the questions in Voltgrid's Nov. 13 project file, which found that Fermi's 600 MW agreement is a non-binding letter of intent for powered land with a customer Fermi has not named, and that Fermi's target for the first AP1000 unit has slipped to 2034.

What the Water Comments Ask For

The NRC's draft EIS says the four units together would provide 4 GW of baseload power directly used by the Matador campus. The NRC says the campus plans 11 GW of on-site generation for an estimated 18 million square feet of AI infrastructure, and puts that 11 GW at roughly 10% of the 111 GW summer capacity ERCOT projects for Texas. The 11 GW is a plan, not built or permitted capacity. The district's comments ask for the data behind the draft EIS's finding that water effects will be small.

The City of Amarillo's website posts a water supply agreement with Fermi, labelled final and dated Oct. 30, 2025, that caps delivery at 2.5 million gallons a day for a 20-year term, at twice the rate the city charges a connection of like size inside city limits. That is a ceiling for the whole Fermi campus, not a stated demand for the reactors. The agreement names the city's Carson County Well Field as the supply, keeps Fermi under the city's drought-contingency curtailment, and makes delivery depend on Fermi building public improvements, including two wells, by January 2027. The city says it has adequate water resources and that the agreement will not affect its supply or trigger changes to its drought plans.

At the same Nov. 19 meeting, the district's board met in closed session with its attorney about what its agenda described as the city's transport of groundwater outside the district and compliance with district rules, the Tribune reported. Assistant City Manager Donny Hooper said city limits fall within two groundwater districts, with some areas outside both, and that the supply is blended from those sources. The board took no action. The Tribune did not say whether the closed-session item involved the Fermi supply.

Where a Draft EIS Sits in Licensing

This is public comment on a draft EIS, not a licence decision. Fermi is seeking a combined licence (COL) to build and operate the four units, filed in parts from June 17, 2025. The NRC reviews safety and environmental effects on the same application, and the draft EIS covers only the environmental half. Under an NRC pilot, Fermi prepared the draft itself under NRC supervision; the NRC must evaluate it independently and take responsibility for its content.

The draft EIS's preliminary recommendation, published in the Federal Register on Oct. 9, is that the NRC issue the COL, contingent on successful completion of the safety review and unless safety issues mandate otherwise. That is a preliminary recommendation, not a decision.

Three steps are done, the comment period closes Nov. 23, 2026, and the final EIS and safety review have no date given; 2034 is Fermi's target for its first AP1000.

Graphic: Voltgrid News

What Is Not Confirmed Yet

The NRC pages read on Nov. 20 give no date for a final EIS or for the end of the safety review, and we found no published comment count. We found no public response from Fermi America to the district's requests.