PEJ's Poland AP1000 Plant: LOI Extends Unit 1 Long-Lead Item Orders
Poland's PEJ and the Westinghouse-Bechtel consortium signed a letter of intent on AP1000 long-lead items for unit 1, World Nuclear News reported Nov. 20; EPC talks target year-end.
6 min read
Follows Poland's PEJ Seeks Permit for Deep Excavations at 3,750 MWe Nuclear Site

AP1000 units under construction at Sanmen, China, in March 2014; not the Polish site. Westinghouse's product page for the design used by PEJ at Lubiatowo-Kopalino.
Image: Westinghouse
Source · Press image from the Westinghouse website, used for news reporting.
Polskie Elektrownie Jądrowe (PEJ), the developer of Poland's AP1000 plant, and the Westinghouse-Bechtel consortium signed a letter of intent at the 7th Ministerial of the Partnership for Transatlantic Energy Cooperation in Warsaw, World Nuclear News reported on Nov. 20, extending their Engineering Development Agreement to the procurement of long-lead items for unit 1 of the three-unit AP1000 plant at Lubiatowo-Kopalino.
The letter is not a contract: it records the parties' intent, and the reports do not say whether any of it binds. Energy Minister Miłosz Motyka described it as the basis for further discussions on the project's key components, and no amounts or duration were disclosed. What it does is keep the slowest-to-make hardware moving while the engineering, procurement and construction (EPC) contract is still being negotiated. That contract is not signed: PEJ and the consortium plan to finish negotiating it by the end of 2026, a target, not a date anyone has met yet. Voltgrid has covered the project once before, on Nov. 2, when PEJ sought a permit for deep excavations at the site; this is our full file on Poland's first nuclear plant.
The technology
The AP1000 is Westinghouse's two-loop pressurized water reactor with passive safety systems. Westinghouse lists a gross rating of 3,415 MWt and a nominal net output of 1,150 MWe per unit. For the plant as a whole, ANS Nuclear Newswire gives total installed capacity of 3,750 MWe for three units. The European Commission's own decision release says up to 3,750 MW, from three reactors of 1,250 MW each, and does not say whether that is net or gross. Westinghouse's 1,150 MWe is its nominal net rating for the AP1000 design, a different figure with a different owner, so the plant total is not three times it.
The one idea that matters here is modular construction. According to World Nuclear News, the reactor building and its systems are made of dozens of prefabricated steel-concrete structural and mechanical modules, built in factories and set in place on site. That shifts schedule risk from the site to the supply chain: if a containment vessel or a wall module is late, the site waits. Westinghouse says six AP1000 units operate worldwide, 14 are under construction and five more are under contract, a vendor figure.
The deal and the money
PEJ is a special-purpose vehicle wholly owned by Poland's State Treasury. Westinghouse supplies the nuclear island and Bechtel is the construction contractor. The parties work under an Engineering Development Agreement, amended on Dec. 29, 2025 to continue design and geological surveys while the EPC contract is negotiated. On Sept. 23, Westinghouse said the consortium and PEJ had agreed the main commercial terms of that EPC contract.
The long-lead work started before this letter. On Oct. 8, Westinghouse said PEJ had commissioned it to begin procuring six key nuclear-island components for unit 1, including the reactor containment vessel and its structural modules. That order covers documentation, supplier selection and materials; production and delivery to the site are to come under a later order under the construction contract. Westinghouse then placed conditional purchase orders for module scopes with four Polish firms, EPG, FAMAK, Mostostal Kielce and Mostostal Kraków, and IHI of Japan received an order covering long-lead engineering and procurement for one containment vessel and a large steel module, World Nuclear News reported.
The new letter adds two things: the parties will work on a mechanism to extend the scopes of contracts critical to the schedule, and the US partners will support PEJ in its talks with export credit agencies on financing component supply. No agency, lender or amount was named.
A letter of intent records what the parties plan to do; it is not the contract. This one extends the Engineering Development Agreement, which keeps design work moving while the main contract is negotiated, to cover orders for long-lead items for unit 1: the parts that take years to make.
The order of events matters for cost and risk. PEJ's chief executive said the components account for a significant part of the project's costs. The EPC contract, which PEJ has said will ultimately determine its cooperation with the consortium, is still unsigned, and the letter discloses no amounts.
The European Commission cleared Poland's support package on Dec. 9, 2025, according to World Nuclear News. Clearance is a ruling that the aid complies with state-aid rules; the transfer of budget funds to PEJ was described as the next step. The package is an equity injection covering about 30% of the project's costs, which World Nuclear News puts at about €14 billion (the Commission's own release gives the 30% but no euro figure), state guarantees on 100% of PEJ's debt, and a two-way contract for difference shortened from 60 to 40 years during the investigation. At least 70% of the plant's annual output must be sold on the power exchange. The Commission puts total capital expenditure at around €42 billion (PLN 178 billion) in nominal terms, an estimate.
Licensing and timeline
PEJ applied to the National Atomic Energy Agency (PAA), Poland's nuclear regulator, for a construction licence on March 31, 2026. The PAA says its president decides within 24 months of submission with the required documents, after a formal and legal check; the period does not count statutory deadlines, suspension periods, or delays by the party's fault or for reasons beyond the authority's control. ANS reported the application ran to about 40,000 pages.
The project already holds an environmental decision, a decision in principle and a location decision, Nuclear Engineering International reported, and preparatory works on site began in autumn 2025. After the PAA licence, PEJ still needs a construction permit from the Pomeranian voivode, which it plans to apply for in 2027.
PEJ's targets, as ANS reported them, are first concrete in late 2028, about seven years of construction per unit and about a year of testing, with commercial operation in 2036, 2037 and 2038. Motyka said on Oct. 8 that the government wants power from the first reactor in 2036. These are targets; a World Nuclear News report from December 2025 cited an earlier aim of 2033.
Done so far, and what is only a target
Done
EU clears Poland's state aid
European Commission ruling that the aid complies with state-aid rules.
Done
Engineering Development Agreement amended
Design work and geological surveys continue while the EPC contract is negotiated.
Done
Construction-licence application filed with the PAA
An application, not a licence; the PAA says it decides within 24 months of submission, with exclusions.
Done
Main commercial terms of the EPC contract agreed
Announced by Westinghouse; the EPC contract itself is not signed.
Done
Westinghouse ordered to begin long-lead items for unit 1
Six nuclear-island components, including the reactor containment vessel; production comes under a later order.
Done
Letter of intent extends the EDA to long-lead items
Reported by World Nuclear News; no separate signing date, terms or amounts disclosed.
Scheduled
EPC contract negotiations to finish
A target set by the parties, not a signing.
Scheduled
Construction-permit application to the Pomeranian voivode
PEJ plans to apply after the PAA licence.
Scheduled
First concrete
PEJ target as reported by ANS.
Scheduled
Unit 1 commercial operation
PEJ target; the energy minister also targets power from the first reactor in 2036.
Scheduled
Unit 2 commercial operation
PEJ target.
Scheduled
Unit 3 commercial operation
PEJ target.
What it means for the AP1000 supply chain and Poland's grid
Poland is ordering long-lead items before it has a construction contract, and PEJ says so: its chief executive said in October that early ordering protects both the schedule and the budget. PEJ and Westinghouse expect Polish companies to bid for contracts provided they obtain ASME NQA-1 certification, and Westinghouse calls the orders a first step for Polish industry to supply the plant and future AP1000 projects in Europe.
That matters beyond Poland. US projects aimed at supplying data centers draw on the same vendor, though no source says they share long-lead parts or fabrication slots. They include Fermi's Project Matador, where Voltgrid reported a non-binding 600 MW letter of intent and an AP1000 target now set for 2034, and Slovakia's Bohunice, where Westinghouse is running a six-month FEED study. If Poland locks in containment vessels and modules first, later buyers may queue behind it; that is an inference, as no source has published a fabrication backlog.
For Poland's grid, the plant would add firm capacity in Pomerania, northern Poland: the European Commission says the plant is scheduled to start operating in the second half of the 2030s, and PEJ's target for unit 1 is 2036. The 70% exchange-sales condition means most of its output would reach the open market rather than a single offtaker.
What to watch
The EPC contract is the next test: the parties target finishing the negotiations by the end of 2026, which is not the same as signing. After that come the PAA's licence decision, with a legal deadline of 24 months from the March 31, 2026 submission, subject to exclusions, the voivode permit application planned for 2027, any export credit agency term sheet, and first concrete targeted for late 2028.
Sources
- 01PAA receives application for licence to construct nuclear power plant at Lubiatowo-KopalinoNational Atomic Energy Agency (PAA)gov.pl
- 02Construction license application submitted for Poland's first nuclear plantANS Nuclear Newswireans.org
- 03PEJ and Westinghouse Begin Long-Lead Item Procurement Process for Poland's First Nuclear Power PlantWestinghouseinfo.westinghousenuclear.com
- 04EU approves Polish state aid for nuclear plantWorld Nuclear Newsworld-nuclear-news.org
- 05Polish nuclear site approvedNuclear Engineering Internationalneimagazine.comas read on Nov 20, 2026
- 06Partners prepare to procure next batch of equipment for Polish plantWorld Nuclear Newsworld-nuclear-news.org