Blue Energy's Port of Victoria SMR: 300 MWe Permit Bid Accepted for Review

Blue Energy says the NRC accepted Part 1 of its permit application for one 300 MWe BWRX-300 in Texas, gas turbines first. Nothing is authorized yet, and Crusoe's AI campus has no disclosed power contract.

Nuclear & Microgrids Desk

5 min read

Rendering of the planned Blue Energy Center at Port of Victoria, Texas: a gas plant and five large buildings beside a river

Rendering of the planned Blue Energy Center - Port of Victoria in Texas, as published by GE Vernova (Blue Energy).

Image: Blue Energy (rendering)

Source · Press image from the GE Vernova newsroom, credited to Blue Energy, used for news reporting.

Blue Energy said on Nov. 16 that the U.S. Nuclear Regulatory Commission (NRC) has accepted Part 1 of its construction permit application for Port of Victoria Nuclear Unit 1, a single 300 MWe BWRX-300 reactor in Victoria County, Texas. The NRC's project page, updated Nov. 16, still shows its docketing letter as a Nov. 16 target, and none is posted yet.

Acceptance means the NRC found the filing complete enough for a detailed safety and environmental review, Blue Energy said. It is not an approval. No construction permit has been issued, and the limited work authorization (LWA) that Part 1 requests has not been granted. Blue Energy also said the NRC accepted its "Blue Hybrid" approach as part of the application; that is the company's description, and an accepted application is not an approval of the approach. Under Blue Energy's plan, subject to a final investment decision in 2027, GE Vernova 7HA.02 gas turbines and the shared balance of plant are built and run first, with GE Vernova Hitachi BWRX-300 small modular reactors added later.

For data centers, the plan is a gas plant first and a nuclear plant later. Crusoe, the AI infrastructure company, plans a 1,600-acre AI campus nearby and has a strategic partnership with Blue Energy, but neither company has disclosed a power purchase agreement, a price, a term or a volume. In 2025 the two companies targeted gas power to the campus as early as 2028 and nuclear generation by 2031, and Blue Energy says the turbines and reactors still depend on a final investment decision in 2027.

The technology

The BWRX-300 is a boiling-water small modular reactor from GE Vernova Hitachi. The NRC's project page lists Unit 1 at 300 MWe, with a dry, single, underground containment, uranium dioxide pellet fuel and natural-circulation, passive cooling.

Blue Energy's idea is to reverse the usual build order. A nuclear plant's turbine hall, cooling and grid connection normally wait for the reactor; here they are built first and fed by gas turbines, which Blue Energy says cuts cost and time to power, and the same balance of plant is later used by the BWRX-300 units. Large plant sections, which Blue Energy calls "Blue Block" supermodules, are to be prefabricated offsite and delivered by barge.

The site's full size is not in the NRC filing, which covers one unit. World Nuclear News reported that the plan announced with GE Vernova Hitachi was an initial 1 GW from two GE Vernova gas turbines, followed by 1.5 GW from up to five BWRX-300 units; Crusoe's 2025 release described a nuclear plant of up to 1.5 GW. Neither source says whether those figures are net or gross.

The deal and the money

Blue Energy is the developer and plans to finance the plant privately rather than through utility rates. It said in September that it had raised more than $400 million, including a strategic investment from Constellation Technology Ventures, and that it had retained Societe Generale to arrange project financing. No project cost has been disclosed.

Blue Energy announced a "project acceleration agreement" with GE Vernova and GE Vernova Hitachi to facilitate deployment of their gas turbines and reactors at the site; GE Vernova Hitachi supplied technical information for the application. No equipment order, price or terms have been disclosed.

Crusoe's side is a strategic partnership announced on Oct. 30, 2025, under which Blue Energy secured the plant site and the power is meant for Crusoe-developed AI factories on a nearby site in Calhoun County. No binding offtake terms have been made public. Blue Energy's Nov. 16 release does not name Crusoe and describes the output as grid-connected power for the state and customers.

Licensing and timeline

Blue Energy filed Part 1 on Sept. 15, 2026, under the NRC's two-step Part 50 process, in which a construction permit allows building but not operation. The NRC's Oct. 8 notice of receipt in the Federal Register says Part 1 contains the LWA request under 10 CFR 50.10(d), two exemption requests, an environmental report and parts of the preliminary safety analysis report, and that the full application is due no later than 18 months after Part 1. The NRC notice says the LWA covers certain early construction activities; Blue Energy says they would be the deep foundations and the shaft for the first reactor. Neither an LWA nor a construction permit lets a plant operate.

The groundwork came earlier: Blue Energy says the NRC approved its topical report on resequencing gas, balance of plant and nuclear island construction in December 2025. Part 2 is targeted for the second half of 2027, after the one calendar year of site data collection the NRC requires.

Blue Energy says the NRC accepted Part 1 on Nov 16, 2026; Part 2 (H2 2027) and nuclear power (2031) are company targets.

Graphic: Voltgrid News

The review schedule is not public yet. On Nov. 18, the NRC project page still listed the draft and final safety evaluation and the environmental assessment as to be determined, pending a schedule letter that had not been posted.

What it means for data centers

The gas-first design is a bid to give an AI campus power on a data-center timeline while the nuclear part works through the NRC. The gas turbines would be the early power, and the nuclear unit waits on the NRC. Its value to Crusoe depends on two things not yet disclosed: a binding supply contract, and how power reaches a campus on a nearby site in Calhoun County. Until then, the firm part of this project is a licence review that has just begun.

The design itself is moving. The NRC issued the first U.S. BWRX-300 construction permit, for the Tennessee Valley Authority's Clinch River site, on Sept. 29 after a 14-month review. The lead unit at Ontario Power Generation's Darlington site will miss its October 2030 target and its C$7.7 billion budget, a reminder that first-of-a-kind schedules slip. In Texas, Dow's Long Mott plant holds an NRC construction permit for four Xe-100 units.

What to watch

The next steps are the NRC's schedule letter and the Federal Register notice on docketing, which the NRC said will also set out how the public can take part; the NRC's decision on the LWA and the two exemptions; Part 2 of the application, targeted for the second half of 2027; the final investment decision planned for 2027; and any power purchase agreement between Blue Energy and Crusoe. Air permits for the gas turbines and the grid connection have not been disclosed.