kt cloud Takes All 60 MW of Keppel's Ansan Data Center Near Seoul

Keppel said on Nov. 26, 2026 its Data Centre Fund III signed kt cloud for all 60 MW of its Ansan site. With Ansan 1, kt cloud's Seoul-area AI capacity reaches 110 MW; service is targeted for 2030.

Chips & Power Desk

3 min read

Key-facts card: kt cloud takes all of Keppel's 60 MW Ansan data center, 100% committed, ready for service in 2030

Keppel's Nov 26, 2026 release gives 60 MW of gross power capacity at Ansan, fully committed by kt cloud.

Graphic: Voltgrid News

Keppel said on Nov. 26, 2026 that its private Keppel Data Centre Fund III (KDCF III) has signed kt cloud as master tenant for the full capacity of its 60 MW greenfield data center in Ansan, South Korea.

Keppel's release says kt cloud committed to take up 100% of the capacity. Construction is expected to begin in November 2026, with service targeted for 2030, and the site already holds construction permits and power approvals. The Edge Singapore carried the same figures. Keppel gave no lease term, rent or investment amount.

Seoul Economic Daily reported that kt cloud calls the project Ansan 2 and that it sits about 2.5 km from Ansan 1, a 50 MW kt cloud data center now under construction. Together the two give kt cloud 110 MW of AI capacity in the Seoul area, according to the newspaper's account of kt cloud's statement. KT Group aims to supply more than 1 GW of AI data center capacity by 2031, so the Ansan pair would be about 11% of that goal.

Ansan 2's 60 MW would bring kt cloud's Seoul-area pair to 110 MW, according to kt cloud's statement as reported by Seoul Economic Daily.

Graphic: Voltgrid News

Why 60 MW Matters Around Seoul

Power is the scarce input in this market. In its June 2026 release on the site, Keppel said recent regulatory measures restrict power supply applications for projects above 10 MW, which curtails the development pipeline. The same release cited a 1.4% vacancy rate in the Seoul Metropolitan Area (JLL, March 2026) and a 2025-2027 supply pipeline that was already fully pre-leased. It put new data center power demand in the area at about 2.3 GW through 2030, so Ansan's 60 MW equals about 2.6% of that projected demand.

The November release adds CBRE Research absorption rates of 99.7% in 2024 and 99.4% in 2025 for Greater Seoul. Keppel describes the 60 MW as secured gross power capacity. Neither Keppel nor kt cloud has said how much reaches servers as IT load, so the figure is not 60 MW of compute. Voltgrid News also covered Alibaba Cloud's sixth Malaysia data center, another Asian AI site.

Building Specs and Keppel's Fund

The building will have two basement levels and eight floors above ground, with about 52,622 square meters of floor area. Keppel says it will meet Tier III-equivalent specifications and include liquid cooling for high-density GPU servers; kt cloud told Seoul Economic Daily that every floor will support it.

For Keppel, Ansan was the second investment of KDCF III, its June release said, and the fund has now made three. Its Funds under Management were about S$5.1 billion at Sept. 30, 2026, against about S$2.7 billion at the end of 2025: roughly 89% growth in nine months. The 60 MW site is under 8% of Keppel's portfolio of 39 data centers with more than 800 MW of gross power capacity at the end of 2025. Voltgrid News also followed NVIDIA's reported Singapore and Malaysia server halt, on the supply side of Asian AI capacity.

What is not confirmed yet

Keppel's November release does not name the Korean co-investors or give kt cloud's stake, lease length or rent. In June Keppel said KDCF III would take about 73% of the land-holding vehicle, with Shinyoung, NH Securities and Hyundai E&C holding 27%. Seoul Economic Daily described kt cloud as a partner in Keppel's first Korean project, while Keppel calls it master tenant; the split between the roles is not public. The 110 MW figure comes from kt cloud's side, not Keppel, and neither site's IT load is published. Watch for the November construction start and any lease or financing disclosure.