Digital Realty 156 MW Rolling Meadows Data Center Wins 4-2 Vote
Rolling Meadows' council approved Digital Realty's $466.9M data center on Nov. 24, backed by a 240 MW ComEd substation, but construction is set to start only by February 2029.
3 min read

The planned campus at 3800 Golf Road in Rolling Meadows, Illinois, by the numbers.
Graphic: Voltgrid News
Rolling Meadows, Illinois, approved Digital Realty's $466.9 million, 156 MW data center campus on a vacant 40-acre office site on Nov. 24, with the city council voting 4-2 on the incentive deal, the Daily Herald reported.
Digital Realty would demolish the shuttered 485,000-square-foot Atrium Corporate Centre at 3800 Golf Road, about 25 miles northwest of Chicago, and build two 2-story data center buildings totaling 975,000 square feet, plus a 2-story ComEd substation. The council granted zoning relief and signed an economic development agreement, and it endorsed the developer's request for a Cook County Class 6B property tax incentive, the Daily Herald said. CBS Chicago reported that the council's vote backs the county giving the incentive; the council itself does not grant the break. Aldermen Kevin O'Brien and Jenifer Vinezeano voted no on the incentive; O'Brien alone voted against the remaining zoning items.
The 156 MW figure is critical power, the electrical load available to IT equipment. The Daily Herald put the ComEd substation at 240 MW, an 84 MW gap that the sources do not explain. Neither outlet gave a GPU count or a tenant.
The planned critical power is 156 MW, against a 240 MW substation rating reported by the Daily Herald.
Graphic: Voltgrid News
Power was the missing piece at 3800 Golf Road
Glen Cole, the city's assistant city manager and community development director, told the Daily Herald in an earlier report that the site never had a clear path to power under its previous owner, because transmission lines along the tollway were tapped out by other data center users in the northwest suburbs. He said ComEd now has a plan to deliver power and that the developer had to post a letter of credit to prepay the infrastructure that gets built.
Digital Realty paid $81.5 million for the site in September, buying from Rosemont-based Brennan Investment Group. Brennan had bought it out of foreclosure for $27 million in 2023.
What the tax deal and conditions say
Under Class 6B, the property would be assessed at 10% of market value for 10 years, then 15% in year 11 and 20% in year 12, against the usual 25% for industrial property. In return, Digital Realty would pay the city at least $49 million, or up to $52 million with inflation adjustments, through 2041. City estimates put property taxes over that period at $159 million for local governments, including $95 million for Palatine Township Elementary School District 15 and Northwest Suburban High School District 214. The vacant office pays about $2 million a year now; the city expects $12.7 million in the first year of operation.
The agreement requires a sound consultant to study noise before construction, after completion and once more if the city asks, with a mitigation plan for any violation. Emergency diesel generators may run only during an outage, when the grid operator orders it, or for routine testing on weekday daytimes unless the city manager approves. Alderman Mike Koehler said the buildings would use closed-loop cooling and far less water than other businesses; no water figure has been published.
Opposition and a long runway
Hundreds of residents filled the chamber and two overflow rooms. Of 31 speakers, six supported the project, including building trades union members, and most of the rest raised water, power and noise concerns; some asked for a referendum. Alderman Nick Budmats said a rejection could have pushed the developer to seek annexation into neighboring Schaumburg.
The timing is slow. The Daily Herald reported that construction is set to begin by February 2029 and finish by June 2031. On that schedule the 156 MW would not be fully available before mid-2031. Elsewhere, cities are pausing instead: Hillsboro, Oregon, extended its data center moratorium on Nov. 17. Digital Realty is also adding capacity abroad, with a $10 billion Japan plan reported on Nov. 15.
What is not confirmed yet
Cook County must still grant the Class 6B incentive. No tenant, GPU count or ComEd in-service date has been published, and the 2029 start is a preliminary timeline. DatacenterDynamics first reported the deal in its paywalled story, which Voltgrid did not read.
Sources
- 01Vacant office complex could become site of first data center in Rolling MeadowsDaily Heralddailyherald.com
- 02Rolling Meadows data center gets tax break at raucous council meetingDaily Heralddailyherald.com
- 03Rolling Meadows approves data center tax incentive for development over residents' objectionsCBS Chicagocbsnews.com
- Published
- Sources
- 3 cited