National Wealth Fund Backs 1 GW/2 GWh of Matrix Scottish BESS
The UK state investor took equity in Matrix Renewables' Eccles and Kilmarnock batteries on Nov. 19, but has not disclosed its stake size. Eccles is due online in October 2027, Kilmarnock in September 2028.
2 min read

Construction at Eccles, one of the two Scottish battery projects Matrix Renewables is developing with the National Wealth Fund.
Image: Matrix Renewables
Source · Press image from the Matrix Renewables newsroom, used for news reporting.
The UK's National Wealth Fund said on Nov. 19 that it has made an equity investment in two Matrix Renewables battery projects in Scotland, Eccles and Kilmarnock, totalling 1 GW of power and 2 GWh of storage.
Matrix keeps a majority stake in both projects, the fund said in its release. The fund did not state the size of its investment, ESS News noted on Nov. 20. The two sites are described as strategically placed along the transmission corridors between Scotland and England, and the fund expects more than 200 jobs to be created or supported across construction and operation. Matrix said the two projects are its first investments in the UK.
The numbers add up to a two-hour battery fleet: 1 GW of power against 2 GWh of energy means the sites can discharge at full output for about two hours. ESS News gives each site as 500 MW/1 GWh. The fund says the projects are meant to help manage network constraints and enable greater integration of renewable energy, which puts the storage on the route that carries Scottish wind power toward England. The fund also said the two facilities together will hold storage equivalent to the annual electricity consumption of around 520,000 households.
At full output the combined 1 GW and 2 GWh of storage at Eccles and Kilmarnock would last about two hours.
Graphic: Voltgrid News
Eccles Is Already Under Construction
Construction is already underway at Eccles, in southern Scotland, and commercial operation is expected in October 2027, according to the fund. ESS News reported that Matrix had previously targeted the third quarter of 2027, so the October date lands just after that quarter. Kilmarnock is expected to begin construction in December 2026, with commercial operation targeted for September 2028.
According to ESS News, Eccles reached financial close in April on GBP 245 million ($321.2 million) of non-recourse debt from CIBC, MUFG and NatWest. Tesla is the engineering, procurement and construction contractor, and EDF will provide route-to-market services and optimize the battery's trading across UK power markets. Matrix is backed by TPG Rise, ESS News said.
How It Compares
The fund has backed British storage before. ESS News lists its participation when Fidra Energy reached financial close on its 3.1 GWh Thorpe Marsh project, a GBP 50 million equity investment in AMP Clean Energy, and a place in an Equitix-led consortium investing in a UK battery developer. At 2 GWh, this pair is smaller than Thorpe Marsh, and far smaller than the 24 GWh US portfolio that EQT agreed to buy from Flatiron Energy, as Voltgrid reported on Nov. 18.
The siting matters more than the size. Voltgrid News reported earlier on Eastern Green Link 3's Scottish licence for a 2 GW subsea link, another piece of the plan to carry Scottish power south. Eccles and Kilmarnock add storage along that route, where the Link adds transmission.
What Is Not Confirmed Yet
The size of the National Wealth Fund's equity cheque and Matrix's retained percentage have not been published. The fund's release does not name a contractor or a route-to-market partner for Kilmarnock, which is the detail to watch when construction starts in December. Both sites are still projects: Eccles has no operating date before October 2027, and Kilmarnock has not yet started construction.