EQT to Buy Flatiron Energy, a 24 GWh US Battery Storage Portfolio
EQT agreed on Nov. 17 to buy Hull Street Energy's Flatiron, with 6 GWh contracted and 2 GWh under construction. The price is undisclosed, and closing is expected in Q4 2026.
2 min read

Image from the website of Energizar, Flatiron Energy's 1,200 MWh storage project in Chelsea, Mass., which is due to operate in late 2027.
Image: Energizar / Flatiron Energy
Source · Press image from the Energizar project website, used for news reporting.
EQT Transition Infrastructure agreed on Nov. 17 to acquire Flatiron Energy, a US battery storage developer with a 24 GWh portfolio, from Hull Street Energy; EQT did not disclose a price.
According to EQT's release, Flatiron develops, builds, owns and operates utility-scale storage in New England, New York and the Mid-Atlantic. Since Hull Street's first investment in 2022 the portfolio has grown nearly ten-fold, 6 GWh of it has won long-term contracts, and 2 GWh is in construction. The deal is subject to customary conditions and approvals and is expected to close in the fourth quarter of 2026, EQT said.
Of Flatiron's 24 GWh portfolio, EQT says 6 GWh has long-term contracts and 2 GWh is in construction.
Graphic: Voltgrid News
What 24 GWh means in practice
The headline figure is a pipeline, and only part of it is contracted or being built. On EQT's numbers, 6 GWh of contracts is 25% of the 24 GWh, and the 2 GWh in construction is about 8%. Flatiron's own Energizar project in Chelsea, near Boston, is rated at 250 MW and 1,200 MWh, or 4.8 hours at full power, according to ESS News. At 1.2 GWh it is roughly 60% of the 2 GWh now under construction, on Voltgrid's arithmetic, though the 2 GWh is a rounded company figure. ESS News reported that Flatiron secured about $850 million in construction and term financing for Energizar, with operation due in late 2027.
For scale, the portfolio is 1.5 times the 16 GWh of cells Samsung SDI agreed to supply to Jupiter Power, as Voltgrid reported. The two figures are not the same kind of number: one counts projects, the other counts cells for delivery from 2029. It is also about four times the 5.9 GWh that Calibrant Energy counts in operation, construction or development, according to our earlier report.
Demand behind the deal
EQT said storage capacity in Flatiron's markets is expected to rise from 2 GWh operating in 2026 to 108 GWh in 2035, as older plants retire and demand grows. That is a 54-fold increase on EQT's own forecast, and the release gives no breakdown by state or by customer. EQT, which says it has more than 100 data centers in its portfolio, framed the purchase as adding firm capacity for a strained grid. The release says nothing about linking Flatiron's projects to its data center business.
The purchase follows EQT's earlier battery investments in Statera Energy in the UK and Ju:niz Energy in Germany. ESS News said EQT plans to support delivery of the contracted projects and expansion into new markets. Simpson Thacher & Bartlett and Santander advised EQT, while Kirkland & Ellis and Guggenheim Securities advised Flatiron.
What is not confirmed yet
EQT declined to give ESS News a price. ESS News also noted September reporting, cited to The Wall Street Journal, that bidders discussed an equity valuation of $400 million to $600 million; that is a bidders' discussion range, not the agreed price. Closing still depends on approvals, and neither company has said which of the 24 GWh sits at which stage of development. What to watch next is the close in the fourth quarter and whether EQT names new markets beyond the three regions Flatiron serves today.
Sources
- Published
- Sources
- 2 cited