NTPC Green Names Khavda BESS Winners: Pace Digitek Has 1,800 of 3,300 MWh
NTPC Green Energy announced winners for its 3,300 MWh Khavda battery auction on Nov. 25, per Mercom India. Pace Digitek's 600 MW/1,800 MWh award is the only one confirmed so far.
2 min read

An NTPC Green Energy solar plant. The company's image library does not label the site, so this is not a picture of the Khavda batteries.
Image: NTPC Green Energy
Source · Press image from the NTPC Green Energy website, used for news reporting.
NTPC Green Energy (NGEL) announced the winners of its auction for 3,300 MWh of battery energy storage systems (BESS) at the NTPC Renewables (NTPC REL) solar plant in Khavda, Gujarat, Mercom India reported on Nov. 25, 2026.
The one award Voltgrid can confirm in full is Pace Digitek's. The Indian company said it won an engineering, procurement and construction (EPC) order worth INR 2,691 crore (INR 26.91 billion) for a 600 MW/1,800 MWh system, according to the company's figures as pv magazine India reported on Nov. 16. The order covers Block-01 and Block-02, each 300 MW/900 MWh, under Cluster-01 of the Khavda project, and includes 15 years of operations and maintenance, Renewable Watch said.
That is 1,800 MWh of the 3,300 MWh, or about 55%. Each block is a three-hour system on the tender's figures: 900 MWh at 300 MW. The remaining 1,500 MWh is one more 300 MW/900 MWh block and one 200 MW/600 MWh block, according to the tender as pv magazine India described it on Oct. 9. Mercom's piece says winners were named for the whole auction, but Voltgrid could not read the part of its report that lists them.
Only 1,800 MWh of the 3,300 MWh tender has a confirmed winner; the 1,500 MWh remainder is Voltgrid arithmetic.
Graphic: Voltgrid News
What the Pace Digitek order implies
Pace Digitek's order works out to roughly INR 15 million per MWh (INR 26.91 billion over 1,800 MWh). That figure is Voltgrid's arithmetic on the company's contract value. It covers supply, integration, civil works and 15 years of operation, so it is a turnkey price and not a cell or pack price. It is also not a tariff, and none has been published for this auction in the reports Voltgrid read.
The company said its status as a Class-I local supplier, which requires at least 50% local content by value across goods, services and works, was an important factor in the win. It cited 5 GWh of installed domestic BESS manufacturing capacity, which it plans to raise to 10 GWh by the third quarter of fiscal 2027, and an in-house container fabrication plant.
Why Khavda matters for Indian storage
Khavda is a solar plant, and the tender pairs the batteries with it. All four blocks sit at one pooling substation, PSS-1, at the NTPC REL site, and the tender specifies a 25-year design life for the batteries on a one-cycle-per-day duty, pv magazine India reported. For grid operators, 3,300 MWh in one place moves solar output into the evening peak at a single connection point. For cell suppliers, an order of this size rewards makers with local assembly.
The domestic-content test links this auction to India's cell policy. Voltgrid reported earlier on India's battery PLI scheme, which had built 1.4 GWh of its 50 GWh target with no incentive paid. Domestic pack assembly is growing in the same state, as Waaree's 5.15 GWh pack line in Rola, Gujarat shows.
What is not confirmed yet
Voltgrid could not read the body of Mercom India's report, which is behind a login, and Voltgrid did not find NGEL's own announcement. The winners of the other two Cluster blocks, 1,500 MWh in all, are therefore not confirmed here, and neither are their contract values. Pace Digitek's figures come from the company as pv magazine India and Renewable Watch carried them. Its delivery date and any tariff or price comparison with other Indian BESS auctions are not confirmed either.
Sources
- Published
- Sources
- 3 cited