ONE Nuclear Scouts Iowa Land for 1,000 MW SMR Plant, No Site Chosen
ONE Nuclear Energy told the Des Moines Register on Nov. 25 it is seeking land in Cerro Gordo County for a 1,000 MW SMR plant; no site, reactor design or buyer is named.
3 min read

ONE Nuclear's 1,000 MW figure is a company target; SOO Green's 2032 date is also a target.
Graphic: Voltgrid News
ONE Nuclear Energy, a West Palm Beach, Florida developer, said on Nov. 25 that it is looking for land in Cerro Gordo County and neighboring counties in north Iowa for a 1,000 MW small modular reactor (SMR) plant, according to the Des Moines Register.
Christopher Hansmeyer, the company's chief development officer, told the Register by email that ONE Nuclear plans to reach the 1,000 MW with SMRs backed by battery storage. The company has not named a site, a reactor design or a vendor. The Register described the facility as a "multi-billion dollar" build; the SEC release carries no cost figure. Hansmeyer also said ONE Nuclear does not plan to ask for eminent domain powers and will seek land through voluntary agreements with private owners.
The project is called Northern Pike. ONE Nuclear's third-quarter release of Nov. 16, filed with the SEC, lists it as a 1,000 MW SMR project in Cerro Gordo County with battery storage still "TBD" and its off-take described only as PJM market access through a letter of intent with SOO Green. A letter of intent is not a power sale: ONE Nuclear told the Register it neither reserves transmission capacity on SOO Green nor obliges either company to sign anything further.
What 1,000 MW would mean in Iowa
For scale, 1,000 MW is about 1.6 times the 615 MW Duane Arnold plant that NextEra Energy is restarting near Palo for Google, a restart targeted for 2029, as Voltgrid reported. The Register notes that SMRs generate about 300 MW each, citing the International Atomic Energy Agency, so a 1,000 MW plant would take three to four modules on that basis. That is Voltgrid's arithmetic, not a company design.
Northern Pike's 1,000 MW is a company target; Duane Arnold's 615 MW restart is reported for 2029.
Graphic: Voltgrid News
ONE Nuclear's chief investment officer called the planned output firm, dispatchable and carbon-free in the Nov. 5 announcement, but nothing ties it to a data center. The company says it can serve hyperscale data centers that face multi-year waits for grid power, yet Northern Pike is aimed at the PJM market over the planned 2,100 MW SOO Green underground line running about 350 miles from Mason City to Yorkville, Illinois. The company said on Nov. 25 that this does not rule out supplying customers inside Iowa.
Timeline and money
ONE Nuclear said it expects nuclear generation in Iowa could begin in the mid-2030s, while SOO Green targets commercial operation in 2032. In the Register's account, the line has Iowa Utilities Commission approval from 2023 and a deadline extended to September 2027. The SOO Green letter of intent, signed on Nov. 5, was the first public step.
The developer is early-stage and thinly funded. Its Nov. 16 release reports $1.5 million of cash on Sept. 30, 2026, a $1.0 million advance since then and a quarterly core burn rate of $0.8 million, and says it intends to raise equity, project debt and customer co-investment. It lists over 7.0 GW of planned generation across five platforms, including 1,000 MW of SMR capacity in each of its Louisiana and Washington State plans.
What is not confirmed yet
No reactor design, vendor, fuel plan, site, offtaker or Nuclear Regulatory Commission application has been named for Northern Pike, and the company said its plans remain subject to definitive agreements, approvals and financing. Voltgrid did not find a Cerro Gordo County board action on the project. The company has also not said how much battery storage it would add. Next, watch for a named site, a reactor vendor and any customer agreement.