Wylfa SMR Project: Three Rolls-Royce SMR Units, at Least 1.4 GWe
Wylfa SMR plans three Rolls-Royce SMR units of 470 MWe each on Anglesey for GBE-N. FID is expected in 2029, World Nuclear News reports, and grid power is a mid-2030s ambition. No data-center buyer is named.
4 min read
Follows Rolls-Royce SMR Aseismic Bearing Demonstrator Completed, 470 MWe Design

Rendering of a Rolls-Royce SMR plant, from Rolls-Royce. It is a generic design rendering, not the Wylfa site.
Image: Rolls-Royce
Source · Press image from the Rolls-Royce website, used for news reporting.
Great British Energy - Nuclear (GBE-N) plans its Wylfa SMR project on Anglesey around three Rolls-Royce SMR units of at least 1.4 GWe in total, by GBE-N's figure. On Nov. 18, 2026, Skanska UK announced it had completed a construction demonstrator for the design, the latest milestone for a project still before its final investment decision (FID).
The demonstrator, an aseismic bearing pedestal built and trialled at Skanska's Bentley Works in Doncaster, is a supply-chain test rather than a licence step, as Voltgrid reported on Nov. 18. GBE-N named Wylfa as the site of the UK's first small modular reactors in November 2025. For data-center planners the question is how firm that supply is and when it arrives: World Nuclear News reports that the FID is expected in 2029, and the government's ambition is power to the grid from the mid-2030s.
The Rolls-Royce SMR 470 MWe Design
The Rolls-Royce SMR is a small pressurised water reactor rated at 470 MWe per unit, according to World Nuclear News and the Office for Nuclear Regulation (ONR); neither says whether that is net or gross. The design is meant for baseload generation over at least 60 years, World Nuclear News reported. Its central idea is factory building: about 90% of the plant is to be built in factory conditions, in modules about 16 m by 4 m, with site work mostly assembly, Rolls-Royce SMR says. That is why off-site trials such as the Doncaster pedestal count. Aseismic bearings isolate the reactor building from ground movement, and Skanska says the demonstrator proved the pedestal can be precast off site.
GBE-N said on Nov. 13, 2025 that the project will deliver up to 1.5 GW of low-carbon energy to the grid. Its April 2026 contract announcement puts the first three units at a minimum of 1.4 GWe, enough for around three million homes by GBE-N's estimate. GBE-N assesses that the site could potentially host up to eight SMRs in the longer term.
Contract and Funding for Wylfa
GBE-N, an arm's-length body of the Department for Energy Security and Net Zero, signed a contract with Rolls-Royce SMR on April 13, 2026, it said in a statement. GBE-N says the contract covers site-specific design, regulatory engagement and planning ahead of a future FID, and will require Rolls-Royce SMR to work with GBE-N to deliver against key milestones. Rolls-Royce SMR calls it a firm contract to develop the site-specific design and order critical components from the supply chain, World Nuclear News reported. Its value was not disclosed. Rolls-Royce SMR chief executive Chris Cholerton said the contract unlocks delivery of the first three units.
What it does not do is commit construction or sell the plant's output. GBE-N said in November 2025 that the SMR programme is backed by £2.5 billion of government funding, and in April 2026 that £2.6 billion was allocated in the 2025 Spending Review to enable the contract and the wider programme; neither release says how the two figures relate. The National Wealth Fund committed up to £599 million to Rolls-Royce SMR, which World Nuclear News described as a loan on commercial terms to support the generic design. None of the official releases states a revenue model, such as a contract for difference or a regulated asset base, for the plant's output.
Licensing and timeline
The design, not the site, is under review. ONR's page shows the Rolls-Royce SMR generic design assessment (GDA) in Step 3 since July 2024, with the assessment of the reactor design ongoing and no completion date given. Step 1 ran from April 2022 to April 2023 and Step 2 from April 2023 to July 2024. A GDA is an assessment of a design and would not license Wylfa itself. GBE-N says its contract covers regulatory engagement and planning processes, and no site-licence or planning application for Wylfa is named in the official releases. The FID is expected in 2029, according to World Nuclear News, and mid-2030s grid power is the government's ambition, not a schedule.
Done
GDA Step 1: done
ONR generic design assessment of the Rolls-Royce SMR design. Completed.
Done
GDA Step 2: done
Completed. The assessed design is the 470 MWe Rolls-Royce SMR.
Under way
GDA Step 3: ongoing
Assessment of the reactor design is ongoing; ONR gives no end date.
Done
Wylfa named as site: done
GBE-N confirmed Wylfa, Anglesey, as the site of the UK's first SMRs.
Done
GBE-N and Rolls-Royce SMR sign contract: done
Starts site-specific design, regulatory engagement and planning ahead of a future FID.
Done
Aseismic bearing demonstrator announced: done
Skanska UK completed the pedestal demonstrator, reported by World Nuclear News. A supply-chain test, not a licence step.
Scheduled
FID expected: planned
Final investment decision expected in 2029, according to World Nuclear News; the party is not named.
Unconfirmed
Grid power: government ambition
A target, not a schedule: the government's ambition for Wylfa SMRs to supply power to the grid.
What Wylfa Means for Data Centers
The government paired Wylfa with an AI Growth Zone. Its Nov. 13, 2025 release confirmed a North Wales zone spanning the Menai Strait, at Prosperity Parc on Anglesey and at Trawsfynydd in Gwynedd, and said it has the potential to leverage the Wylfa SMR project. The zone is led by a consortium including Stena Line, the Isle of Anglesey County Council and Bangor University, and as of that release an investment partner was still being sought. No data-center operator, power purchase agreement or supply arrangement from Wylfa is named in the official releases.
The releases describe Wylfa's output as power to the grid. That suggests a campus in the zone would draw grid supply, though the AI Growth Zone release also says investors may develop their own on-site power solutions, so a direct arrangement is not ruled out. If the mid-2030s ambition holds, a campus that opens there before then would run on other supply first. On the sources' own dates, Wylfa is a long-dated option on firm power for British AI campuses, not near-term capacity.
What to watch
The next markers are the end of GDA Step 3, for which ONR gives no date, any site-licence and planning applications for Wylfa, and the FID expected in 2029. For the data-center angle, the test is whether the North Wales AI Growth Zone names an investment partner or an operator, and whether either signs for Wylfa's power.
Sources
- 01AI Growth Zones to create thousands of jobs as new site confirmed for North WalesGOV.UK (DSIT)gov.uk
- 02Contract signed for delivery of UK's first SMRsWorld Nuclear Newsworld-nuclear-news.org
- 03Great British Energy - Nuclear and Rolls-Royce SMR sign contractGreat British Energy - Nuclear (GOV.UK)gov.uk
- 04Wylfa confirmed as site for UK's first small modular reactorGreat British Energy - Nuclear (GOV.UK)gov.uk
- 05Generic Design Assessment: Rolls-Royce SMROffice for Nuclear Regulationonr.org.ukas read on Nov 27, 2026
- 06Prototype aseismic bearing completed for Rolls-Royce SMRWorld Nuclear Newsworld-nuclear-news.org
- Published
- Sources
- 6 cited