Châteauroux Data Center: Google, ENGIE MoU Only Studies Heat Reuse
ENGIE signed an MoU to be Google's preferred energy partner for the Châteauroux data center, but free waste-heat supply is only a study item. Phase one is 120 MW on 225 kV, per DCmag.

Solar panels in an ENGIE illustration image from the Nov. 13 release; not a photo of the Châteauroux site.
Image: ENGIE
Source · Press image from the ENGIE newsroom, used for news reporting.
ENGIE said on Nov. 13 that it signed a memorandum of understanding (MoU) with Google that could make it Google's preferred energy supplier and manager for the planned Châteauroux data center in France, subject to later agreements.
The release says the work would run along three lines: new renewable generation, grid integration and flexibility including battery storage (BESS), and local energy infrastructure. Both companies would also study recovering the data center's waste heat and supplying it free of charge to local heating networks or other heat users. The release gives no heat volume, no recipient and no investment figure. ENGIE adds that the identified solutions would only be developed further if the data center goes ahead.
Why the Heat Reuse Pledge Is Only a Study
The headline pledge is a study item, not a delivery contract. Nothing published sizes the heat against any network's demand. The power side is the larger question: ENGIE says new renewable capacity must not push up electricity prices for households or businesses locally or nationally, a condition that will be tested against the grid load described below.
Châteauroux Campus: Site, Grid Load and Cooling
Google's project sits in the Ozans industrial zone at Étrechet, just south of Châteauroux. According to French data-center trade magazine DCmag, the site covers about 195 to 200 hectares and would hold six to eight buildings over 10 to 20 years, down from ten in the first dossier. The first building is now pencilled in around 2030, against 2028-2029 in the referral to the national public-debate commission, the CNDP.
DCmag reports that phase one connects to RTE's 225 kV network for 120 MW, and that phase two needs a 400 kV connection and at least one more building. Final power estimates diverge, from more than 500 MW to 1.1 or 1.2 GW; Google has not set a figure in any document we read. For scale, the roughly 500 MW Google Hermantown data center in Minnesota, covered earlier by Voltgrid News, sits at the low end of that range.
Regional broadcaster ICI reported that Google plans air cooling, with about 1,000 cubic metres of water per building injected once into a closed circuit, and cites 1,800 to 2,600 permanent jobs counting direct, indirect and induced posts.
What Is Still Unconfirmed on the Project
ENGIE calls the data center a project Google "envisages", and the MoU is conditional on later agreements. A CNDP-supervised consultation runs from Nov. 2, 2026 to Jan. 10, 2027, according to ICI. The CNDP then has one month to publish its report and the project owners two months to answer open questions, before the commission gives an opinion and the permit and public-inquiry stages begin.
The CNDP-supervised consultation closes Jan. 10, 2027; the first building is reported for around 2030.
Illustration (AI-generated)
Heat tonnage, the heat network's owner and price, the renewable portfolio's size and the final grid load are all unpublished. Local opposition is active: ICI reports that four Étrechet municipal councillors walked out in protest at the project.
Sources
- 01ENGIE and Google plan Châteauroux data center that could heat the townGoogle News · data centersnews.google.com
- 02ENGIE and Google sign MoU on energy for planned data center near ChâteaurouxENGIE Newsroomnewsroom.engie.com
- 03Où en est le projet de data center XXL de Google à Châteauroux ?DCmagdcmag.fr
- Editor
- Ege Erten
- Published
- Sources
- 3 cited
- Standards
- AI-assisted