Nebius Leases 134 MW More From Mega Or in Israel, Due Q2 2028

Mega Or's third lease with Nebius adds 134 MW of IT capacity at Beit Shemesh and Masmiya, but the Masmiya grid connection is still frozen by Israel's Electricity Authority.

Chips & Power Desk

3 min read

Visualization of the Mega DC campus in Beit Shemesh, Israel: grey data center halls above olive scrub

Mega DC's Beit Shemesh campus, as shown on the company's Our Sites page; image appears to be a visualization, not a photo of the finished halls (Mega DC).

Image: Mega DC

Source · Press image from the Mega DC website, used for news reporting.

Nebius signed a third lease with Israel's Mega Or for 134 MW of IT capacity, with both data centers due by the end of Q2 2028, CTech by Calcalist reported on Nov. 19.

The agreement covers two sites: one under construction in Beit Shemesh and one planned in Masmiya, within the Yoav Regional Council. Mega Or announced it that day through Mega DC, the subsidiary that holds its data center business, and the counterparty is a subsidiary of Nasdaq-listed Nebius, according to CTech. Mega Or estimates the new contract will add NIS 550 million in average annual net operating income (NOI) once fully occupied, on top of the NIS 740 million it already expects from earlier data center contracts. DatacenterDynamics (DCD) put those at $164.74 million and $221.65 million.

"MW IT" is the power allocated to computing equipment alone, so it excludes cooling and other facility loads. Total grid draw at both sites will be higher than 134 MW; neither report gives that figure.

Two Sites, Two Different Grid Positions

The Beit Shemesh facility, designated MDCIL-4, is the second phase of Mega DC's campus there. It is under construction, has a grid connection approval and has a maximum capacity of 135 MW of IT load. The first phase, 58 MW, is covered by the January agreement, and CTech said Nebius could take possession of it this quarter to begin fitting it out.

Masmiya is the weak link. CTech said Mega Or's latest quarterly report classed the Masmiya site (MDCIL-7) as land earmarked for future development, and that the Electricity Authority has frozen the processing of its grid connection application. Approval of that connection is a prerequisite for finalizing the transaction with Nebius. The two reports do not split the 134 MW between the sites.

Cost, Term and Footprint

Mega Or estimates the construction bill for both facilities at about $1.6 billion, based on $12 million per MW of IT capacity, CTech reported. Nebius gets a seven-year service term that starts on delivery, with an option to extend it by five years on the same terms.

Set against the earlier deals, the lease is the largest yet. Mega DC signed the first with Nebius in May 2025 for 8 MW at Modi'in. The second, on Jan. 6, 2026, covered 80 MW: 58 MW at Beit Shemesh and 22 MW at Masmiya, at an investment Globes put at $880 million. By Voltgrid's arithmetic, the three agreements add up to 222 MW of IT capacity, and the January deal's $880 million works out to about $11 million per MW against the $12 million per MW Mega Or now assumes.

The 134 MW lease is the largest of Nebius's three Mega DC agreements, which add up to 222 MW of IT capacity by Voltgrid's arithmetic.

Graphic: Voltgrid News

For Nebius the lease lands as spending climbs. As Voltgrid reported, Nebius raised its 2026 capital-spending guidance to about $27 billion with its third-quarter results on Nov. 12, and it signed a preliminary deal for up to 50 MW in Saudi Arabia last month. In Israel it is a tenant, with Mega Or carrying the construction cost.

What is not confirmed yet

Mega Or's own filing with the Tel Aviv Stock Exchange could not be read for this story, so the figures above come from CTech's account of the company's announcement and DCD's follow-up, which cites CTech. Neither report quotes Nebius. The MW split between Beit Shemesh and Masmiya is not stated, and the Q2 2028 completion date covers both sites even though Masmiya still lacks a grid connection approval. Watch for the Electricity Authority's decision on that application, and for Nebius taking possession of the first Beit Shemesh phase this quarter.