Lea County Google Data Center Gets $130B Bond in 4-1 Vote
Lea County commissioners approved a $130 billion industrial revenue bond for Google's Project Rancho near Hobbs, NM, on Nov. 19. Power demand was not stated and the lease was still under negotiation.
3 min read

The commission approved the bond 4-1 on Nov. 19 and rejected a six-month moratorium on data center development, according to local reports.
Graphic: Voltgrid News
Lea County commissioners in New Mexico voted 4-1 on Nov. 19 to approve a $130 billion industrial revenue bond (IRB) for Google's proposed Lea County data center, Project Rancho, several miles west of Hobbs, the Albuquerque Journal reported.
The vote, at the commission's public meeting in Lovington, came with the same board unanimously rejecting a proposed six-month moratorium on data center development, according to the Journal. Commissioner Sims cast the lone vote against the IRB and against Local Economic Development Act funding, saying he wanted another month to weigh the terms. The Journal said the IRB does not involve borrowing money: the county leases the project property to the developer in exchange for payments in lieu of taxes and other community investments or services, subject to a community benefits agreement. Former Hobbs Mayor Sam Cobb told KOB 4 the payments would flow to local governments, schools and hospital districts.
Project Rancho Site, Water and Timeline
According to a presentation by Google executive Chris Adams, as described by the Journal, the project sits on nearly 1,900 acres and would have two 900,000-square-foot buildings, a closed-loop cooling system and power from a large-scale solar array. KOB 4 reports construction starting in 2027 and operations in 2029, which the Journal narrows to the second half of 2029. Google projects more than 1,000 construction jobs at peak and more than 100 operational jobs across the data center and the solar facility.
Google's presentation to Lea County puts Project Rancho at two 900,000-square-foot buildings on nearly 1,900 acres; these are vendor figures and power demand was not stated.
Graphic: Voltgrid News
Water is the most specific figure in the record. A slide in the presentation put construction demand at 2.8 acre-feet, or 912,384 gallons, per day, and Google estimates up to 28 acre-feet a year per building once the site is running. Adams said Google intends to use effluent or imported water. He did not state the initial fill volume for the cooling system.
Power Demand Google Has Not Disclosed
The $130 billion is the size of the bond authorization for the lease structure, not a capex figure from Google and not a capacity figure, and no source Voltgrid read gives the data center's critical IT load or its grid interconnection in megawatts. The Journal noted that the presentation left out how much power the facility would need for operations. Without that number, the scale of the solar array and of any grid or on-site backup cannot be compared with other campuses, such as the roughly 500 MW Hermantown project Voltgrid covered on Oct. 31.
The county does set conditions on power. In February, commissioners passed a resolution saying that incentivized AI and data center projects must generate their own power or take it from the public grid, guard against local rate increases, protect water, and sign a decommissioning agreement. The Hobbs mayor's statement, published by KOB 4, welcomed the same protections for groundwater and for existing electric customers.
Opposition and Approval Process
Lovington resident Clayburn Griffin presented a moratorium petition with hundreds of local signatures. He told KOB that a resident survey found 96% of 800 signatures opposed the project, a figure from a small group of neighbors rather than a formal poll. Griffin said residents wanted independent town halls and never got them. Voltgrid News reported earlier on San Jose's data center moratorium.
Commissioners Sims and Gary Eidson conceded that the approval looked rushed. Peter Franklin, an attorney for the county's bond counsel, said it is normal in IRB deals for some terms to be unsettled at the vote, with authority delegated to a county manager or the commission chairman to approve final documents later. Open-government advocates argue the practice moves public business out of view. The Journal likened the process to the IRB for Oracle and OpenAI's Project Jupiter in Doña Ana County.
Voltgrid could not locate the Nov. 19 agenda packet, the ordinance text or the lease on the county's site, so the figures above come from the Albuquerque Journal and KOB 4, and the $130 billion should be checked against the ordinance. The lease, the community benefits agreement and the payment schedule were still under negotiation at the vote, per the Journal. Neither outlet gives the data center's megawatts or the solar array's capacity. Griffin said New Mexico lawmakers are expected to debate protections for rural communities when the session opens in January.