SpaceX Arizona Data Center: AG Asks County to Delay Dec. 9 Vote on 6 GW

Arizona AG Kris Mayes asked Cochise County on Nov. 19 to delay its Dec. 9 vote on SpaceX's Arizona data center, citing an unexplained power gap and water use; no delay is reported.

Chips & Power Desk

2 min read

Follows SpaceX Linked to 6 GW Cochise County, Arizona Data Center Plan

Key-facts card: Arizona AG asks Cochise County to delay Dec. 9 vote on SpaceX data center, up to 6 GW

The Arizona attorney general's Nov. 19 letter asks the county to delay its Dec. 9 vote on SpaceX's proposed campus, which could draw up to 6 GW.

Graphic: Voltgrid News

Arizona Attorney General Kris Mayes asked Cochise County on Nov. 19, 2026 to delay its Dec. 9 vote on SpaceX's proposed Arizona data center campus, which could draw up to 6 GW, according to her office.

Mayes sent the letter to the county's Planning and Zoning Commission, which is scheduled to decide the special use permit, her office said in a release. She asked it to wait until state and federal agencies finish their reviews. KJZZ, which first reported the request, described the letter as going to the Board of Supervisors; the AG's release names the commission. Her office will also seek more information from SpaceX and has set a public town hall for Dec. 3, 5:30 p.m. to 7 p.m., at Cochise Elementary School.

The letter lands about two weeks after SpaceX acknowledged the project at a public meeting. As Voltgrid reported on Nov. 9, the county application (SU26-22) was filed by Tombstone Resources LLC for about 747 acres near Cochise. On Nov. 12 SpaceX put roughly $50 billion on the Arizona campus, Voltgrid reported from Reuters.

Power is the central objection

The AG's release says the campus could use nearly 20 percent of Arizona's current generating capacity. According to azfamily's summary of the letter, the campus needs 1.5 GW at start-up and 6.0 GW at full buildout. The letter says start-up demand alone is 62% larger than the entire owned and contracted generation fleet of Arizona Electric Power Cooperative, whose Apache plant produces roughly 625 MW.

Start-up demand alone is 1.5 GW, against an Apache plant of roughly 625 MW, according to azfamily's summary of the AG's letter.

Graphic: Voltgrid News

SpaceX has proposed $3.6 billion in grid investment, azfamily reported, but the letter says it has not explained how it would close the 4.5 GW gap. For scale, KJZZ noted that the Arizona Public Service utility's peak demand record this year, across all its customers, was 9,164 MW.

Water, fire and other concerns

The application describes a dry-cooled campus using 7 to 10 acre-feet of water a year. The letter says that figure leaves out the water needed to generate the power: one 1 GW natural gas plant running continuously withdraws 3.6 million to 6.8 million gallons a day, according to azfamily. The site lies in the Willcox Active Management Area, which the state designated to curb groundwater depletion.

The letter also cites about 6,150 Tesla Megapack batteries on a site outside any fire district, up to 5,500 workers at peak construction on rural US-191, the nearby Willcox Playa where sandhill cranes winter, and possible interference with Army electronic testing at Fort Huachuca.

If the commission votes on Dec. 9 anyway, Mayes recommends at least four conditions: delay the permit's effective date and hold building permits until all state and federal authorizations are in hand, assess the full 6 GW rather than phases, and hold more public meetings. KVOA reported that the City of Willcox has asked SpaceX for a local meeting and a voluntary 2:1 groundwater conservation offset, and had not received a response.

What is not confirmed yet

A search of reports through Nov. 21 found no commission decision to postpone and no SpaceX statement answering the letter. The county's project page, last updated Nov. 12, still lists the Dec. 9 hearing and says the applicant's figures have not been independently verified. The 1.5 GW, 62% and 4.5 GW figures come from azfamily's account of the letter, which Voltgrid did not read in full. Whether the commission delays, and how SpaceX would supply the power, are the open questions before the Dec. 9 hearing.