NVIDIA GTC DC, Huang Senate Hearing Dec. 3: AI Chips and Power Week Ahead
NVIDIA CEO Jensen Huang is the sole witness at the Dec. 3 Senate Banking hearing, while GTC Washington, Marvell, TSMC Arizona and DOE's Eddystone deadline frame the week for AI hardware.
2 min read

NVIDIA's event graphic for GTC Washington, D.C., which runs Nov. 30 to Dec. 3, 2026.
Image: NVIDIA
Source · Press image from the NVIDIA event page, used for news reporting.
NVIDIA's GTC Washington, D.C. runs Nov. 30 to Dec. 3, Marvell reports on Dec. 1 and CEO Jensen Huang is the only witness at the Senate Banking Committee's Dec. 3 export-controls hearing, a week that tests AI chip demand, policy and the power behind it.
Huang's Senate Banking hearing on Dec. 3 falls mid-week; the Dec. 2 and Dec. 4 dates are reported, not confirmed by the organizers.
Graphic: Voltgrid News
NVIDIA's event page lists workshops on Nov. 30 and the conference and expo on Dec. 1 to 3 at the Ronald Reagan Building and International Trade Center, with sessions on AI factories and gigawatt-scale compute. On Dec. 3 at 10:00 a.m. the committee meets in open session, in hybrid format, in Dirksen 106 for a hearing titled "Protecting America's AI Advantage: Oversight of U.S. Export Controls." Its notice names Huang as the witness. Voltgrid covered the setup in Huang's sole-witness hearing.
For compute buyers the question is where advanced accelerators can ship. Export rules decide which sites receive racks, and each rack adds load to a site that still needs a grid connection. The hearing is a policy event, not a ruling: the notice lists no rule change.
Dec. 1 to 2: Marvell's call and Brazil's first battery auction
Marvell said in a Nov. 6 release that it will hold a conference call following its third-quarter fiscal 2027 results on Tuesday, Dec. 1, at 1:30 p.m. Pacific Time. The call gives investors Marvell's own account of its data infrastructure chip business.
Brazil's first capacity-reserve auction for batteries (LRCAP) is set for Dec. 2 and is open only to systems that meet BNDES local-content criteria, according to pv magazine Brasil. A second auction on Dec. 4 carries no nationalization requirement. The cut in the Fundo Clima rate to 3% for Brazilian-made packs, approved on Nov. 26, lowers the nominal financing cost from 7.88% to 4.34% a year for projects on the local-content routes.
Dec. 4 to 5: TSMC in Phoenix and DOE's Eddystone deadline
On Dec. 4 TSMC is due to hold a groundbreaking event in Phoenix. AZFamily reported on Nov. 25 that President Donald Trump is expected to attend, a visit first reported by Bloomberg and later confirmed by Gray's Washington bureau, and that other details have not been made public. Voltgrid's earlier report on the TSMC Arizona groundbreaking has the background.
Under U.S. Department of Energy Order No. 202-26-52, PJM must give the Department by Dec. 5 information on the measures it has taken and plans to take to keep Eddystone Units 3 and 4 operationally available. The order runs from Nov. 21 to Feb. 18, 2027 and covers two units of 380 MW each. Voltgrid's Eddystone order report covers the earlier orders.
What is not confirmed yet
As of Nov. 29, none of these events has taken place, and this piece does not predict their outcomes. The TSMC phase being broken ground is not specified in the reports Voltgrid read. The Brazil auction dates are as reported by pv magazine Brasil, and the Marvell results arrive with the call itself.
Sources
- 01Marvell announces conference call to review third quarter of fiscal year 2027 resultsMarvell Technologyinvestor.marvell.com
- 02NVIDIA GTC Washington, D.C. 2026: event pageNVIDIAnvidia.comas read on Nov 29, 2026
- 03President Trump to attend latest TSMC groundbreaking in Phoenix next weekAZFamilyazfamily.com
- 04Protecting America's AI Advantage: Oversight of U.S. Export Controls (hearing notice)Senate Banking Committeebanking.senate.govas read on Nov 29, 2026
- 05DOE Order No. 202-26-52: Eddystone Units 3 and 4U.S. Department of Energyenergy.gov
- 06CMN reduz juros do Fundo Clima de 6,5% para 3% para baterias fabricadas no Brasilpv magazine Brasilpv-magazine-brasil.com
- Published
- Sources
- 6 cited