Section 48D Chip Credit: Cornyn-Kelly S.5809 Adds 5 Years to 35%

Senators Cornyn and Kelly announced S.5809 on Nov. 20 to extend the 35% fab tax credit five years. It lapses for plants that start building after Dec. 31, 2026.

Chips & Power Desk

2 min read

The U.S. Capitol dome and the Senate wing in Washington under a clear blue sky

The U.S. Capitol, where the Senate is weighing S.5809. The image is a general view from the Semiconductor Industry Association's release page, not a photo of the bill's introduction.

Image: Semiconductor Industry Association

Source · Press image from the Semiconductor Industry Association newsroom, used for news reporting.

Sens. John Cornyn (R-TX) and Mark Kelly (D-AZ) announced S.5809 on Nov. 20 to extend the 35% Section 48D chip-factory credit by five years; current law ends it for projects that start building after Dec. 31, 2026.

BusinessKorea reports that the bill was proposed on Nov. 19, local time, and referred to the Senate Finance Committee. The Semiconductor Industry Association (SIA) welcomed it in a statement dated Nov. 21 and urged Congress to pass it before it adjourns for the year. The bill is a week old, and nothing in the sources we read shows a committee vote or a floor date.

Why the Dec. 31 date matters

Section 48D, the Advanced Manufacturing Investment Credit, equals 35% of an eligible taxpayer's qualified investment in a chip or chip-equipment plant, according to Cornyn's office. On a $1 billion qualifying outlay that is $350 million (Voltgrid's arithmetic). The test is when construction begins, not when a fab opens: BusinessKorea says a plant that breaks ground from 2027 under current law gets nothing.

SIA says the credit has supported more than $825 billion of announced private investment across more than 160 projects in 30 states. That is a pipeline of fabs, and each new phase now faces the cutoff.

Which projects sit on the line

Samsung told shareholders on July 30 that it will break ground on its second Taylor, Texas, fab by the end of 2026, with that building expected online in 2030, the Austin American-Statesman reported. That start falls inside the current window. A later slip would not.

TSMC's Brazos County, Texas, application, as Voltgrid reported, shows construction starting in 2027 on a proposed $22.6 billion 2nm campus, after the current cutoff. TSMC has said its Texas plans remain under evaluation, and none of the sources says the company is counting on 48D. At TSMC's Phoenix site, a groundbreaking is planned for Dec. 4, but its scope is unspecified, so we cannot say which phase it would lock in. The sources we read give no 48D timing for Micron or Intel projects.

Samsung's planned Taylor groundbreaking falls inside the current Section 48D window; TSMC's reported 2027 Brazos County start falls after the Dec. 31, 2026 cutoff.

Graphic: Voltgrid News

Who is pushing

Senate Finance Chair Mike Crapo (R-ID) and ranking member Ron Wyden (D-OR) called for an extension in a joint statement on Aug. 5, Thomson Reuters Checkpoint reported. Former Intel CEO Pat Gelsinger wrote on LinkedIn on Nov. 24 and asked Congress to extend the credit to 2032, a year beyond the Senate bill, according to BusinessKorea. SEMI, the equipment and materials trade group, also wants materials and design covered.

What is not confirmed yet

We could not open the bill text on Congress.gov, so how S.5809 moves the construction-start date is unconfirmed: Cornyn's office and SIA say five years, and BusinessKorea says the application deadline moves back five years. Whether the 35% rate stays is also unconfirmed. The next signals are a Finance Committee markup or a year-end tax package that carries the extension.