Taipower Plans NT$109.6B Grid Build for 8 GW Tainan Chip Parks

Taipower expects the Greater Tainan science parks to need 8 GW and plans about NT$109.6 billion of substations and a 345 kV line, but has given no completion dates.

Energy & Cooling Desk

3 min read

Key-facts card: Taipower plans NT$109.6bn of substations and a 345 kV line for the Tainan chip parks, 400 MW/km2 forecast density

Taipower's planned grid package for the Greater Tainan science parks, as carried by Economic Daily News and NOWnews.

Graphic: Voltgrid News

Taipower, Taiwan's state utility, said on Nov. 22 that it plans about NT$109.6 billion of substations and a 345 kV line to supply the Greater Tainan science parks, where it expects demand to reach 8 GW (800萬瓩).

According to Economic Daily News, which carried the utility's statement, the package has three parts: new substations for the Nanke special zone and the Shalun park, a 345 kV Hsinta-Nanke transmission line, and new substations at neighboring industrial zones. NOWnews reported the same three items. DigiTimes carried the plan in English on Nov. 25; that report is paywalled, so this story rests on the two Taiwanese outlets.

Taipower defines the Greater Tainan science parks as the Tainan, Nanke special-zone, Shalun and Shugu sites, about 20 square kilometers in all. At 8,000 MW over that area, the load works out to 400 MW per square kilometer, which the utility described as the world's highest power density. It said Tainan City's long-term demand could pass 10 GW, and that the concentration is a severe test of thermal stability, voltage quality and fault tolerance.

What the Money Buys and What It Does Not

The NT$109.6 billion works out to about NT$13.7 billion per GW of projected demand, a Voltgrid calculation from Taipower's two figures. It is a wires-and-substations budget. Taipower said separately that five approved direct-supply lines from power plants to science parks need about NT$155.5 billion, with works finishing between 2026 and 2033. NOWnews stressed that the two budgets must not be added together. The direct-supply lines include one from the Hsinta plant and the Senba independent power producer (IPP) to Nanke and Shalun.

Local Supply Is the Gap

Taipower says Tainan has only 1.1 GW of stable local generation, the Senba phase 1 and 2 units, and leans on the Hsinta plant for the rest. Hsinta's first gas-renewal phase added three combined-cycle units with 3.9 GW of capacity this year, according to Economic Daily News. Taipower is pressing Tainan to host its own stable supply, including a planned privately owned Senba phase 3, and warned that relying only on cross-region transfers carries high system risk.

Taipower's 8 GW demand forecast for the Tainan parks compares with 1.1 GW of stable local supply, according to Economic Daily News.

Graphic: Voltgrid News

For chip fabs, which run around the clock, the point is that an 8 GW forecast is about seven times the 1.1 GW of local supply now named. The new lines and substations move power in; they do not create it. The utility also said that approving park substations early, speeding land acquisition and permits, and charging users for temporary supply and rush costs would keep construction in step with demand.

TSMC, the parks' largest investor according to Economic Daily News, is also expanding abroad, as Voltgrid reported in its $22.6 billion Texas campus tax filing. In the United States, utilities have asked FERC for 10 to 20 year data-center grid upgrade contracts, a way to make large loads pay for the wires built for them.

What is not confirmed yet

Taipower has not given completion dates for the substations or the Hsinta-Nanke line in the reports Voltgrid read, and the reports do not say how the NT$109.6 billion will be funded or phased. Land acquisition and permits are named as the main schedule risk. Economic Daily News says the National Science and Technology Council is planning a large new park for future 1 nm fabs, with Shalun development expected to start in 2027, but no fab schedule or load figure has been published for it. The 8 GW figure is Taipower's long-term estimate, not a contracted load.