Utilities Ask FERC for 10-20 Year Data Center Grid Upgrade Contracts
PJM, MISO, California and New York utilities want FERC to approve 10 to 20 year contracts with collateral; in some states they would be a data center's only long-term transmission commitment.
2 min read

Proposal terms as reported by Latitude Media; FERC has accepted none of them.
Graphic: Voltgrid News
Transmission-owning utilities in PJM, MISO, California and New York have asked the Federal Energy Regulatory Commission (FERC) to approve contracts of 10 to 20 years that make data centers pay for the grid upgrades they trigger, Latitude Media reported on Nov. 18.
The filings answer FERC's June 18 show-cause orders, which asked each grid operator and its transmission owners to fix gaps in large-load rules. For PJM, the docket is EL26-67-000, and the order called for a pro forma cost recovery agreement among PJM, the transmission owner and the customer, according to the PJM transmission owners' own notice. The PJM owners committed to file by Nov. 16, and Utility Dive confirmed their tariffs set out rates, cost allocation, financial protections and revenue crediting.
What a data center would sign
In PJM's region, a data center would commit to pay for at least 80% of the transmission service it requests for a minimum of 10 years, Latitude Media reported. It would post collateral starting at 25% of what it would owe and rising to the full amount by the time service begins, and one that leaves early would owe the remainder. California and New York utilities propose 15 years. In MISO, the grid operator itself proposed a three-way agreement with the utility and the customer running up to 20 years, and MISO said its pro forma cost recovery agreements are designed to prevent cost shifts onto existing customers.
Proposed minimum terms run from 10 years in PJM to up to 20 years in MISO; all are proposals.
Graphic: Voltgrid News
Why it matters for connection timing
Interconnection speed is only half of the data center queue problem; the other half is who carries the upgrade bill. As Voltgrid reported, PJM's Fast Energization plan targets a single one-year study. These contracts attach a long payment obligation to the result, before the upgrades are built.
The terms differ from what states already demand. A Latitude Intelligence analysis puts the average minimum commitment at 12 years for PJM utilities with state transmission tariffs and 15 years in MISO, so the federal proposals would be shorter in PJM and longer in MISO. Dominion's Virginia tariff and AEP Ohio's tariff set minimum bills of 85% over 14 and 12 years respectively.
Where the federal contract would stand alone
In retail-choice states such as New Jersey and Pennsylvania, a utility's minimum bill generally does not apply, so the FERC agreement would be a data center's only long-term transmission commitment, Latitude Media said. The same holds in Northern California, where PG&E reports a 12.9 GW data center pipeline and no minimum term. New York's 15-year contract would not take effect until May 2028, so Niagara Mohawk's customers face no long-term commitment until then.
The PJM utilities say their proposal does not govern retail service, and they asked that existing utility-data center contracts count where they give comparable protection. That could leave a Virginia data center on its state contract and a Pennsylvania one on the federal agreement.
What is not confirmed yet
FERC has accepted none of these proposals. Comments on several are due Dec. 7, and the Southwest Power Pool is due to file by Nov. 20. FERC rejected most of PJM's previous large-load plan in October, partly for reaching into retail territory, and it may take issue with contracts signed directly with data centers. The terms above are as Latitude Media and Utility Dive report them from the filings. Other pending filings, such as ISO New England's large-load tariff, are on the same track.
Sources
- 01Grid operators file closely watched large load interconnection reforms at FERCUtility Diveutilitydive.com
- 02Notice of PJM Transmission Owners Consultation with the Members CommitteePJM Interconnectionpjm.com
- 03Utilities want FERC to lock data centers into paying for grid upgradesLatitude Medialatitudemedia.com
- Published
- Sources
- 3 cited