MISO MTEP26 Plan: $14.7B, 532 Projects, Over Half Large-Load Driven
MISO's board committee cleared the $14.7 billion MTEP26 transmission plan, RTO Insider reported, with the full board vote targeted for Dec. 3 and cost assignment for data-center load disputed.
3 min read

MISO's MTEP26 transmission plan, as reported by RTO Insider; the full board vote is targeted for Dec. 3.
Graphic: Voltgrid News
A committee of MISO's board, at a meeting MISO had scheduled for Nov. 12, cleared the grid operator's 2026 Transmission Expansion Plan, known as MTEP26, a $14.7 billion portfolio of 532 projects in which more than half the cost traces to large-load additions, RTO Insider reported on Nov. 15.
The full MISO board is expected to take the final vote on Dec. 3. MISO's Planning Advisory Committee minutes of Oct. 7 put the System Planning Committee meeting on Nov. 12 and board approval of the portfolio on Dec. 3, 2026. RTO Insider described stakeholders as doubting that consumer protections on large loads are strong enough.
What the $14.7 billion buys
Large loads are the main driver. The Transmission Owners told MISO in feedback posted Oct. 12 that load additions drove more than 26 GW of approved new demand and a record 89 Expedited Project Reviews, MISO's expedited study process. The Environmental Sector, another stakeholder group, said eight of the ten most expensive projects went through that fast track, and three exceed $1 billion each.
The total has moved. RTO Insider reported on Oct. 14 that the plan fell to $14.74 billion from an earlier $17 billion estimate, and the Environmental Sector asked MISO to explain the drop. The same group said the report holds 100 more projects and $2.4 billion more investment than last year's, calling it the most expensive MTEP portfolio in MISO's history without a regional long-range portfolio.
RTO Insider reported that MTEP26 fell to $14.74 billion from an earlier $17 billion estimate.
Graphic: Voltgrid News
Who pays
The dispute is over cost assignment. The Environmental Sector wrote that MISO has no project type for upgrades required to connect a large load, so there is no clear route to charge those costs to the customer causing them rather than spreading them across a Local Resource Zone. By its count, load-growth projects are less than a quarter of the "Other" projects by number but 47% by cost.
The Transmission Owners answered that retail agreements already cover several of the biggest projects. They said Michigan regulators approved agreements for the large load behind Project Cannoli, No. 6 on MISO's top-10 list, with an estimated net benefit to other customers of about $1.7 billion over 2028-2047. They added that customer agreements for the West Fork Creek-St. Landry 500 kV line in Louisiana, No. 1 on that list, are meant to cover its cost through the large load's revenues. These are the owners' statements, not MISO findings.
The owners also said they and MISO expect to file tariff changes at FERC by Nov. 16, with approval requested effective January 2027. They would add a pro forma cost-recovery agreement meant to keep large-load costs from shifting to other transmission customers, following FERC's June 2026 show-cause order.
Regional split and other MISO dockets
Voltgrid News has covered MISO's larger lines, including the 187-mile Iowa 765-kV project. The Environmental Sector said MISO South holds 69% of the 66 Baseline Reliability Projects while representing about one-third of MISO load. MISO's minutes say none of the top ten projects involve HVDC, and some are 500 kV facilities. In a separate matter, FERC approved tougher MISO penalties on demand response in October.
What is not confirmed yet
RTO Insider's full report was behind a paywall, so the committee's vote count and the meeting date were not confirmed in the pages Voltgrid News read. The Dec. 3 board vote is a target in MISO's schedule, not a result, and the feedback figures come from stakeholders, not from MISO. MISO's posted figures for the share of cost driven by large loads were not available to us.
Sources
- 01$14.7B MTEP 26 Clears MISO Board Committee VoteRTO Insiderrtoinsider.com
- 02MISO: Draft MTEP26 Report, Appendices FeedbackMISOmisoenergy.orgas read on Nov 15, 2026
- 03MISO Planning Advisory Committee minutes, October 7, 2026MISOcdn.misoenergy.orgas read on Nov 15, 2026
- 04Large Loads a Force Behind Nearly $15B in MTEP 26RTO Insiderrtoinsider.com
- Published
- Sources
- 4 cited