National Grid's 90 km, 400 kV Humber Line Accepted for Examination
The Planning Inspectorate accepted National Grid's 90 km, 400 kV North Humber to High Marnham application on Nov. 12; consent is not granted, and operation is targeted for 2031.
3 min read

The Planning Inspectorate accepted the 90 km North Humber to High Marnham link for examination; the £553m figure is an earlier estimate, as reported.
Graphic: Voltgrid News
The Planning Inspectorate accepted National Grid Electricity Transmission's application for the North Humber to High Marnham link for examination, its project page shows in an update dated Nov. 12, 2026: a new 400 kilovolt (kV) connection of about 90 km in northern England.
The line would run between a new substation at Birkhill Wood, north of Hull in the East Riding of Yorkshire, and a new substation at High Marnham in Nottinghamshire, according to the Inspectorate. Construction Enquirer reported on Nov. 13 that National Grid's earlier strategic assessment put the wider scheme's capital cost at £553 million, made up of £338 million for overhead lines and £215 million for substation works. That is the basis of the "£550m" in the trade-press headline: an earlier estimate, not a newly confirmed construction cost.
What it means for grid capacity and AI load
For US readers, this is a Great Grid Upgrade project, National Grid's programme to add transmission capacity in England and Wales. National Grid says the line is meant to move more power south from the Humber region, where offshore wind comes ashore, and project director Monica Corso Griffiths said demand for electricity is growing. None of the pages we read ties the line to data centres or AI load, and none gives its capacity in MW.
The link to data-center load is indirect: large loads in Britain wait on transmission reinforcements like this one, and the timeline is long. If consent is granted, construction is expected to begin in 2028 and the connection to be operational in 2031, Construction Enquirer and the Newark Advertiser reported. Acceptance does not change available capacity today.
Construction in 2028 and operation in 2031 are reported targets that depend on development consent.
Graphic: Voltgrid News
Where the process stands
The Inspectorate's page puts the project at the pre-examination stage. Acceptance means the application is complete enough to examine; it is not approval. Anyone who wants to take part must register as an interested party, and the applicant sets that registration period, which must run at least 30 days, according to the Inspectorate's general guidance. That guidance says pre-examination usually takes about three months, the examination up to six months, the Inspectorate then has three months to send its recommendation, and the Secretary of State for Energy Security and Net Zero has three months to decide. Those are the statutory stage lengths, not a timetable published for this project.
The two substations are handled through separate planning applications. Construction Enquirer said Birkhill Wood received planning permission in February 2026 and High Marnham in June. It also reported that Laing O'Rourke is preparing to serve as principal contractor for enabling works along 46 km of the overhead route. Transformer Magazine reported that a community fund of about £18 million would be available if development consent is granted.
Context and what comes next
The scheme sits alongside other National Grid transmission work Voltgrid has covered. The Eastern Green Link 3 marine licence clears one consent for a 2 GW subsea link, with operation aimed for 2033, and National Grid's Teesside substation land purchase is aimed at a neighbouring data centre. Britain's offer of priority to data-center sites that pass its tests is a Treasury policy paper, not legislation.
What is not confirmed yet
Development consent has not been granted, and the Secretary of State has not decided. The registration deadline for interested parties was not on the pages we read. The line's capacity in MW and any final cost are not stated: the £553 million figure is the earlier assessment, and one outlet's "£550m" headline rounds it.
Sources
- 01North Humber to High Marnham - Project information (EN020034)Planning Inspectoratenational-infrastructure-consenting.planninginspectorate.gov.ukas read on Nov 15, 2026
- 02National Grid advances 90 km linkTransformer Magazinetransformer-magazine.com
- 03£550m Humber to Midlands pylon project clears first hurdleConstruction Enquirerconstructionenquirer.com
- 04National Grid development consent order application for North Humber to High Marnham acceptedNewark Advertisernewarkadvertiser.co.uk
- Published
- Sources
- 4 cited