Texas Resumes Data Center Air Permits as ERCOT Audit Nears Dec. 10
TCEQ resumed normal data center permit reviews after ERCOT finished gathering community-impact data; full findings go to the PUC Dec. 10, so approvals now run ahead of the audit.
3 min read
Follows SpaceX Starbase Air Permit: Texas Approves 35 Turbines, 750 MW Off-Grid

Key dates and figures in the Texas data center permit restart, as reported by The Texas Tribune.
Graphic: Voltgrid News
The Texas Commission on Environmental Quality (TCEQ) has resumed normal review of air and other environmental permits for data center projects across Texas, ending a pause that Gov. Greg Abbott ordered while ERCOT, the state grid operator, gathered information on the projects.
TCEQ received notice from Abbott's office on Friday, Nov. 13, that ERCOT had finished collecting information on the community impacts of data centers, the Texas Tribune reported. "The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement.
The first visible result is the Starbase permit: TCEQ cleared SpaceX's gas-turbine plant on Nov. 16, as Voltgrid reported. The restart now reaches every other data center applicant in the state.
Why Texas Data Center Permits Matter for Grid Planners
A data center that plans to generate its own power needs an air permit before it can burn gas, and one that connects to the grid needs ERCOT's sign-off. Texas had two gates closed at once. With the environmental gate open again, projects that were waiting on TCEQ can move toward construction while ERCOT's own review is still unpublished. That shifts the question from whether sites can be permitted to how much of the load ERCOT will end up planning for.
ERCOT gave the Public Utility Commission of Texas (PUC) a progress update on Nov. 5. It said it had received responses from 93% of 465 projects, enough for what it called "a statistically meaningful analysis for the final report," according to the Tribune. ERCOT plans to present full findings to the PUC on Dec. 10 and to discuss them at the PUC's next open meeting on Dec. 17.
ERCOT reported answers from 93% of 465 projects on Nov. 5, before TCEQ received notice on Nov. 13 and resumed reviews.
Graphic: Voltgrid News
Abbott's Permit Pause and Its Dates
Abbott called in August 2026 for an ERCOT and regulator audit of data centers seeking grid connections, with a pause on new interconnection approvals while it ran, the Tribune reported. His letter to TCEQ asking for the environmental permitting pause is dated Sept. 21, 2026, and told the agency to wait until ERCOT "completes its review," according to the Tribune.
Enforcement of the pause was uneven. The Tribune reported that Public Citizen and FracTracker Alliance found in October that some data center construction permits were still being cleared. TCEQ said it suspended those permits and shut down its automated electronic filing system, requiring physical applications.
Politics Around the Restart
Abbott lost his Nov. 3 re-election bid to Democrat Gina Hinojosa, who campaigned on keeping data center approvals paused until legislators pass new state law, the Tribune reported. She takes office in January. Public Citizen's Kathryn Guerra said TCEQ was issuing permits without sharing ERCOT's results with communities, and the group called on TCEQ commissioners to resign. Neither Abbott's office nor Hinojosa's team had responded to the Tribune's request for comment on Tuesday.
For operators, the timing is the point: TCEQ approvals can now land weeks before ERCOT's large-load findings and before any new state law. Voltgrid has been tracking that review, including ERCOT's probe of nearly 10 GW of sub-75 MW projects.
What is not confirmed yet
We could not read a TCEQ or governor's office release; the figures and quotes above come from the Texas Tribune and Investing.com, and TCEQ's statement is cited as they report it. The number of permits waiting at TCEQ, and how many it will issue before Dec. 10, have not been published. ERCOT's findings, including whether any project is flagged, are due Dec. 10.