FERC Approves MISO Interconnection Queue Fix for 35 GW

FERC approved changes to the 35 GW MISO interconnection queue: a penalty-free exit before Decision Point II, a single restudy cap, and a higher cost threshold.

Energy & Cooling Desk

3 min read

Abstract editorial illustration of transmission lines and a substation with a waiting row of solar arrays, battery cabinets and wind turbines.

Illustration (AI-generated)

Graphic: Voltgrid News

Washington, Nov. 23 — FERC approved a plan to clear the MISO interconnection queue. The decision targets about 35 GW of active projects in the 2022 study cycle.

The order lands days after a permitting bill cleared 62-33 in the Senate with text that would put data centers under a FERC rule.

The Technical Details: MISO Interconnection Queue

MISO filed the package on Sept. 21, 2026, and FERC set an Oct. 19, 2026 effective date. The order covers the Definitive Planning Phase-2022 (DPP-2022) cycle, which holds roughly 35 GW of active projects in the interconnection queue, the line of projects waiting for a grid connection. Three rule changes were approved: first, projects may exit the queue without penalty before Decision Point II, a checkpoint in the study cycle, which fell on Oct. 20, 2026; second, MISO will conduct no more than one restudy, a fresh grid-impact study run when the project list changes, in the final DPP Phase III for this and all future cycles; third, the penalty-free exit trigger rises to a 50% increase in network upgrade costs, the grid reinforcement costs charged to the developer, from the previous 35% threshold.

FERC rejected Ranger Power's argument that the penalty-free exit rewards bad behavior and is discriminatory. The commission also dismissed Pathway Power's claim that the 50% threshold lacked justification, noting that the same level was already approved for the 2023 study cycle onward and does not unfairly burden small developers.

  • Total MISO queue: nearly 125 GW across almost 600 projects and four study cycles
  • Solar capacity: 44 GW
  • Battery capacity: 25 GW (about 20% of the queue: 25 GW of 125 GW)
  • Wind capacity: about 20 GW
  • Gas capacity: 19 GW
  • Hybrid capacity: 10 GW
  • DPP-2022 active projects: about 35 GW (about 28% of the queue: 35 GW of 125 GW)
  • Delay avoided, per MISO: roughly 18 months for DPP-2022
  • Final-phase restudies: 1 maximum, for DPP-2022 and all future DPP cycles
  • Penalty-free exit trigger: 50% network upgrade cost increase vs. 35% before

DPP-2022's about 35 GW of active projects is about 28% of MISO's nearly 125 GW queue.

Graphic: Voltgrid News

Voltgrid Analysis: Infrastructure Implications

The single restudy cap and the penalty-free exit before Decision Point II should reduce cascading delays that have historically lengthened interconnection timelines across the MISO footprint. MISO's own estimate sets the stakes: without the changes, the DPP-2022 cycle would have slipped by roughly 18 months and dragged other cycles with it. MISO operates the market that will implement these rules.

Battery developers hold 25 GW in the queue, representing 20% of the total 125 GW. The clearer exit and restudy rules give storage projects a more predictable path to commercial operation. A 150 MW / 300 MWh battery project in Texas is one example of the storage capital lining up behind grid access.

Battery projects hold 25 GW, about 20% of the nearly 125 GW MISO interconnection queue.

Graphic: Voltgrid News

MISO's faster queue clearance aligns with its Nov. 16 large-load filing at FERC, which proposes three study cycles in every 365-day period that fold in prior transmission changes to cut restudy risk. The grid operator has also filed a dedicated study for loads of 200 MW or more paired with a generator for at least 15 years.

A proposed GRITS service would let large consumers take part of their demand as non-firm service, meaning interruptible power that MISO can curtail when prices spike. MISO does not expect to launch GRITS before 2029 due to software upgrades, while load-serving entities project 3.1% to 5.1% compound annual load growth over five years, according to POWER Magazine.

Our read: the higher 50% cost-increase threshold raises the financial exposure for projects that choose to stay in the queue, which may affect return calculations for the remaining solar, wind, gas and hybrid projects.

Looking Ahead

Decisions in two other pending FERC dockets will settle the remaining details of the queue reform. The single-restudy cap will apply to all future DPP cycles.