Tatung Wins 345 kV Transformer Orders in Texas, California; 9-Month Lead
Tatung disclosed 345 kV orders in Texas and California at its Nov. 26 conference and says some power transformers ship in 9 months; order value and buyers are not public.
3 min read

Tatung disclosed the 345 kV orders at its Nov. 26 investor conference; order value and customers were not given.
Graphic: Voltgrid News
Taiwan's Tatung said on Nov. 26 it has won 345 kV large power transformer orders in Texas and California, and that some of its power-class transformers can now ship in 9 months.
The company disclosed the orders at its joint third-quarter investor conference, according to reports by UDN, NOWnews and Mirror Media. None of them gives an order value, a unit count, a customer or utility name, or a delivery date for the two orders. President Chang Sung-Pin told Mirror Media that some of Tatung's 161 kV and 345 kV power transformers take 9 months, against 1.5 to 3 years at rivals, and that distribution-class units take 3 to 4 months. Taisounds, reporting the same conference, put the usual rival wait at 12 to 18 months or more, with some US products taking 2 to 3 years.
Tatung's own lead times are 9 months against 12-18 months or 1.5-3 years cited for rivals; no independent data was reported.
Graphic: Voltgrid News
Why it matters: a transformer is often the longest-lead item in a substation, so a supplier quoting 9 months against multi-year waits changes the schedule for any utility or data center developer that needs 345 kV equipment. These are Tatung's own lead times. No independent lead-time data appears in the reports, and Chang himself warned Mirror Media that many key components worldwide still carry lead times of two to three years. Chang said global power-equipment supply is short, and Taisounds reported that Tatung sees order visibility running to 2030.
How Tatung plans to ship into the US
Tatung says it pre-stocked critical parts such as bushings and insulation materials, which is how it explains the shorter lead time, according to Taisounds. It has set up three warehouse hubs in the US West, Central and East, and is evaluating US assembly and strategic partners. Its global chief operating officer told Mirror Media that North American transformer orders taken in 2026 are due to be delivered progressively from 2027.
At home, Taisounds reported that the new Guanyin plant is finished and that expansion works are due to be completed by the end of this year, with the Sanxia motor plant being upgraded. Mirror Media reported that the group is also studying a new plant for 500 kV transformers, in Taiwan or abroad, and developing high-voltage DC (HVDC) equipment that converts 36 kV straight to 800 V DC, plus solid-state transformers (SST). Tesla's version is covered in Voltgrid's report on its 7.4 MW Powercore unit.
The data center order and the money
Tatung also said it has taken its first turnkey Edge AI order for its TTG AIDC CUBE, a modular data center for 0.5 MW to 50 MW sites that it says can be running in 180 days. UDN reported that the order covers a complete power and liquid-cooling module. Tatung said 4 to 5 more Edge AI customers are in talks. For very large data center operators, Taisounds reported, Tatung's pitch is large transformers, power distribution equipment and electromechanical work instead.
Tatung is not the only Asian supplier chasing US grid and data center equipment: LS Electric won a $93.8 million US data center switchgear order earlier in November. For scale, Tatung reported nine-month revenue of NT$36.25 billion and net profit attributable to shareholders of NT$1.88 billion, up 35.5%, or NT$0.89 a share. Taisounds reported that third-quarter profit alone was a loss of about NT$40 million.
What is not confirmed yet
The size of the Texas and California orders, the buyers, the sites and the delivery dates are not public. It is also unclear whether the 9-month lead time applies to those two 345 kV orders or only to some units. We did not find a conference deck on Tatung's investor page or on Taiwan's market observation system. DigiTimes also reported the orders, but its report is behind a paywall.
Sources
- Published
- Sources
- 4 cited