Telus Exits Westbank's 2 Vancouver AI Data Centres, 85 MW BC Hydro Plan

Telus confirmed in a Nov. 14 Daily Hive report that it will not co-develop Westbank's Vancouver AI data centres, which Westbank says will continue with an unnamed partner. The May plan counted on 85 MW from BC Hydro.

Chips & Power Desk

3 min read

Key-facts card: Telus exits Westbank's two Vancouver AI data centres; 85 MW initial BC Hydro power and a 150+ MW cluster target by 2032

Telus's May 11, 2026 plan targeted 85 MW of initial BC Hydro power and more than 150 MW by 2032; Telus has now left the two Vancouver sites.

Graphic: Voltgrid News

Telus is no longer co-developing Westbank's two Vancouver AI data centres, both companies confirmed in a Daily Hive report published Nov. 14, six months after announcing a cluster meant to reach 150 MW by 2032.

A Telus spokesperson said the company "has decided not to proceed with co-developing two previously announced Vancouver data centres with Westbank." A Westbank spokesperson said Telus "is no longer a partner on the two Vancouver projects but we are proceeding with a new partnership." Neither company has named the new partner. Westbank added that it expects to keep working with Telus in other capacities.

The plan Telus announced on May 11, 2026 was a three-site sovereign AI cluster in British Columbia: an expanded Kamloops facility plus the Vancouver sites. In its release, Telus said the cluster would start on an initial 85 MW of power secured from BC Hydro and scale to more than 150 MW and more than 60,000 GPUs by 2032. The release called the work a proposal under the federal Enabling Large-Scale Sovereign AI Data Centres initiative, developed with Westbank and the Government of Canada.

Daily Hive's report does not say what happens to the 85 MW BC Hydro supply now that Telus is out of the Vancouver sites. Telus told the outlet it is still working with the provincial and federal governments and is considering development partners and locations for further expansion elsewhere in B.C., and that it will release more details in the coming months.

What Telus keeps and what Westbank carries on

Telus is expanding its existing Kamloops facility to 20 MW by the end of 2028, according to Daily Hive.

Telus keeps Kamloops at 20 MW by end-2028, while Westbank carries M3 and 150 West Georgia with a partner not yet named.

Graphic: Voltgrid News

Westbank is left with both Vancouver builds. At 111 East 5th Ave. in Mount Pleasant, it wants to convert the six-storey M3 office building into a data centre; Westbank's project website describes M3 as a 26 MW facility. At 150 West Georgia St., a new 10-storey building would sit above Creative Energy's steam plant, where recovered heat from the data centre would help produce steam for the downtown heating network. Telus's May release said it expects the Vancouver sites to recycle waste heat equivalent to heating 150,000 homes. That is a company projection, not a measured result.

Timeline and local approvals

The May release gave M3 an opening at the end of 2026, scaling through 2028, and 150 West Georgia a 2029 start. M3 still needs a rezoning. On July 21, 2026, the previous Vancouver City Council sent the referral report back to staff, pulling it from the July 23 public hearing and asking for more consultation after the October civic election. The city has since scheduled a consultation period for M3 from Dec. 2 to 15, 2026. The 150 West Georgia site needs no rezoning, because a 2023 text amendment already permits data storage use there.

Scrutiny is rising. On Nov. 18, Vancouver City Council is due to consider a motion from Councillor Lucy Maloney that would explore independent assessments of water use, emissions, noise, heat and jobs before rezoning, plus a business licence with annual disclosure of water and electricity use. The motion asks staff for further policy work and would not enact those rules itself. Westbank said it supports the study. Voltgrid News has tracked similar local pushback elsewhere, including protests seeking a moratorium on a 420 MW Anthropic data centre in Nova Scotia, and a tally of moratoriums, lawsuits and votes since Oct. 1.

What is not confirmed yet

The new Westbank partner has not been named by either company. Neither has said who will hold the BC Hydro power allocation for the Vancouver sites, whether the M3 and 150 West Georgia timelines from May still stand, or how the federal sovereign AI initiative treats the change. Telus has not given a reason beyond its spokesperson's statement. The new partnership is Westbank's own statement and has no second confirmation.