Donalds Pushes Florida Nuclear; FPL Plan Puts Any SMR After 2035

Florida Gov.-elect Byron Donalds is pushing SMRs and microreactors, Politico reports, but FPL's April site plan only starts early site permitting in 2026-27 and puts any unit after 2035.

Chips & Power Desk

3 min read

Key-facts card: FPL plan puts any new small modular reactor after 2035; early site permitting 2026-2027; nuclear fleet 3,502 MW

Key facts from FPL's April 2026 Ten Year Site Plan: early site permitting for a potential SMR is planned for 2026-2027, and any SMR in service falls outside the plan period (2035).

Graphic: Voltgrid News

Florida Gov.-elect Byron Donalds wants the state to lay the groundwork for small modular reactors (SMRs) and microreactors, Politico reported on Nov. 28, but Florida Power & Light (FPL) puts any new SMR after 2035 in the plan it filed with the Florida Public Service Commission (PSC) in April 2026.

Donalds told reporters in Tallahassee this month that nuclear power is "cheap, green and affordable," according to Politico. He takes office in about a month.

FPL's 2026-2035 Ten Year Power Plant Site Plan says the utility plans to start early site permitting for a potential SMR in 2026-2027, at a site adjacent to an existing nuclear plant, under Nuclear Regulatory Commission rules. FPL calls the step a way to prepare for SMRs becoming commercially viable, while "remaining cognizant" of the current high costs of nuclear and SMR development. It describes a stepwise approach and says the projected in-service date falls outside the ten-year period the plan covers.

For data-center load, the consequence is timing: no new FPL nuclear unit in the filing enters service before 2036, and the plan has nuclear's share of FPL's energy falling while solar grows.

What FPL's Nuclear Fleet Looks Like Today

FPL runs four nuclear units at two sites, St. Lucie and Turkey Point, with about 3,500 MW of summer capacity. The plan lists 3,502 MW in total: 1,821 MW at St. Lucie and 1,681 MW at Turkey Point. Those units supplied 29,483 GWh in 2025, roughly 20% of FPL's generation, and the filing projects that share at about 16% by 2035 while solar rises from 11% to 26%.

FPL's four nuclear units at two sites provide 3,502 MW of summer capacity, with St. Lucie the larger at 1,821 MW (FPL Ten Year Site Plan).

Graphic: Voltgrid News

FPL also still holds combined operating licenses for two large units, Turkey Point 6 and 7, which the Nuclear Regulatory Commission approved in April 2018. The 2026 plan says their earliest possible in-service dates are beyond the ten-year period, so they are not in the build plan either.

Duke Energy Florida has no nuclear plans, a spokesperson, Ana Gibbs, told Politico. She said its Ten Year Site Plan proposes new solar and upgrades to existing units, and called advanced nuclear "still a longer-term option." Politico also cited a PSC review that expects Florida's nuclear generation to decline slightly over the next decade while solar more than doubles, reaching about 23% of generation by 2035 from about 9% in 2025.

Rules That Would Apply

Under Florida law, nuclear plants above 75 megawatts are subject to PSC review, and a utility can recover construction costs from ratepayers only if the commission finds the project the most cost-effective option, Politico reported. An SMR, which Politico defines as 50 to 350 megawatts, would fall under that test. Other states are further along: Voltgrid reported that the New York Power Authority qualified 10 developers for an Upstate project of at least 1 GW, and that the Tennessee Valley Authority's Clinch River BWRX-300 received the first US construction permit for an SMR of that design with no build decision.

What Is Still Open

FPL has not named a site, a reactor design or a partner, and early site permitting is not a construction permit or a commitment to build. FPL spokesperson Andrew Sutton told Politico that a dedicated team is evaluating SMR technologies. It is unclear what state policy Donalds will propose or how much it could speed a utility plan that places any SMR beyond 2035. Politico notes the US has no commercial SMR or microreactor in operation yet. Watch the next FPL site plan filing for any change to the 2026-2027 permitting window.