TVA Clinch River BWRX-300: First US Construction Permit, No Build Decision
TVA's 10-K says it holds the first US construction permit for a 300 MWe BWRX-300 at Clinch River but has not decided to build. A separate $1.7B data-center commitment names no customer.
5 min read

Rendering of a BWRX-300 plant from GE Vernova Hitachi's product page. It is a generic design illustration, not a view of TVA's Clinch River site.
Image: GE Vernova Hitachi (rendering)
Source · Press image from the GE Vernova Hitachi website, used for news reporting.
The Tennessee Valley Authority (TVA) holds the first US construction permit for a GE Vernova Hitachi BWRX-300 at Clinch River but has not decided whether to build it, the federal utility said in its annual report filed with the SEC on Nov. 13, 2026 (EDGAR accepted it after hours on Nov. 12), as Utility Dive reported on Nov. 24. The same 10-K discloses a $1.7 billion data-center capacity agreement signed on Nov. 10, with the customer unnamed.
The permit is for one BWRX-300 small modular reactor (SMR), which GE Vernova describes as a 300 MW design and World Nuclear News as 300 MWe, at TVA's Clinch River site in Oak Ridge, Tennessee. The Nuclear Regulatory Commission (NRC) dated its construction permit decision Sept. 28, 2026. GE Vernova Hitachi says it is the first US construction permit for a BWRX-300, a light-water SMR. For data centers, it is still not firm supply: no build decision, cost estimate, construction contract or buyer for its output has been disclosed. TVA says any decision to build a reactor needs its Board's approval.
How the BWRX-300 Boiling Water SMR Works
The BWRX-300 is a boiling water reactor: water boils in the core, and the steam drives the turbine directly, with no separate steam generator. It is a 300 MWe, water-cooled design that circulates its coolant naturally rather than with pumps and relies on passive safety systems, World Nuclear News reported, and it builds on the design and licensing basis of GE Hitachi's larger ESBWR. The sources do not say whether the 300 MWe is net or gross.
That lineage is the one idea that matters for timing: the design leans on an existing licensing basis, and it has a first unit under way elsewhere. The first BWRX-300 is already under construction at Ontario Power Generation's Darlington site in Canada, the first of four planned there, as Voltgrid's project file on Darlington sets out. Canada's regulator issued OPG a licence to construct in April 2025, and OPG applied for a licence to operate in March 2026, GE Vernova said.
TVA Funding and the $1.7B Data-Center Commitment
No construction contract has been disclosed. TVA said after the permit that it continues to negotiate with industry partners on cost sharing, and Mike Skaggs, then interim president and CEO (named permanent CEO on Nov. 10, 2026), said on Sept. 30 that the priority is that the Valley's customers do not carry the cost of a first-of-a-kind unit, according to World Nuclear News. The 10-K names a multi-party collaborative arrangement, signed in December 2022, to advance the BWRX-300 globally; GE Vernova Hitachi is responsible for the standard design.
The money disclosed so far is development money. The TVA Board approved $350 million for its New Nuclear Program, and TVA had spent $290 million of it by Sept. 30, 2026. The program expired that day, but in August the Board removed the cap, so future advanced-reactor spending goes through the normal budget. Counting the early site permit work, TVA had spent $381 million on SMRs by Sept. 30, of which $40 million was reimbursed. In December 2025, the Department of Energy selected TVA and co-applicants to negotiate a grant for Clinch River. That is a selection to negotiate, not an award, and no amount is disclosed.
The $1.7 billion is a separate agreement. It falls under TVA's new Capacity Commitment Charge for data-center loads above 5 MW, priced at about $1.5 million per MW of requested capacity above 5 MW, a rate TVA says may change for later customer cohorts. TVA gets $31 million on signing and the rest in 59 installments. The filing names neither the customer nor its capacity, and does not tie the payments to Clinch River.
Clinch River Construction Permit Timeline
TVA took an early site permit first, then applied for a construction permit under the NRC's route of a construction permit followed by an operating licence. The early site permit, issued in December 2019 and valid through 2039, found the site suitable and lets TVA build itself or let third parties build and own projects there. TVA filed the construction permit application in two parts, the environmental report on April 28, 2025 and the preliminary safety analysis on May 20, 2025, and the NRC completed its acceptance reviews on June 12, 2025 (environmental report) and July 9, 2025 (safety analysis), which the 10-K describes as acceptance for review in July 2025. GE Vernova dates the application to April 2025 and the 10-K to May 2025; the NRC's two filing dates explain the gap. The final supplemental environmental impact statement followed on April 6, 2026, the final safety evaluation on June 25, and the mandatory hearing on Aug. 13. The NRC finished in 14 months, four months ahead of its schedule, World Nuclear News reported. It had earlier granted an exemption that let TVA excavate before the permit.
Every NRC licensing step is complete through the Sep 28 construction permit decision; the TVA Board build vote, an operating licence application and first power have no dates, per the NRC and TVA's 10-K.
Graphic: Voltgrid News
A construction permit is the NRC's go-ahead to build a nuclear plant, not to run it: loading fuel and operating the reactor need a separate NRC operating licence, and the NRC's Clinch River page lists no operating licence application. Until TVA's Board approves construction, the permit is a licence held in reserve, and nobody has contracted for the output. TVA has announced no construction date, and the filing gives no date for first power.
What Clinch River Means for Data Centers
TVA is lining up several tracks at once, and gas is the one with a Board-approved target date. In August its Board approved 1,550 MW of gas generation targeted online in 2032, subject to environmental reviews, with up to $3.1 billion more to spend. On nuclear, it has a power purchase agreement for up to 50 MW from Kairos Power's Hermes 2 plant, as early as 2030, and an agreement with ENTRA1 Energy to explore up to 6 GW of NuScale-based plants, which has no PPA yet, as Voltgrid reported. Against those, Clinch River is the project where TVA itself holds the construction permit, and it waits on TVA's own decision.
The new data-center tariff suggests how that decision could be paid for. Skaggs said on the Nov. 13 earnings call that the rate change has supported investment, Utility Dive reported. If large-load customers commit capacity payments up front, TVA has a source of cash for new supply without passing first-of-a-kind cost to existing customers. The filing does not say that any of it will go to Clinch River.
What to Watch Before TVA Decides to Build
The TVA Board vote on whether to build is the milestone that turns a permit into a project, and none is scheduled. Watch for the DOE grant award and its amount, a construction contract and cost estimate, a named offtaker, and an operating licence application. TVA's next quarterly report, for the quarter ending Dec. 31, is the next filing where any of these could appear. Darlington's progress, and Blue Energy's Texas BWRX-300 application filed in September, will show how far the design's licensing experience carries.
Sources
- 01NRC issues first U.S. construction permit for a BWRX-300 small modular reactor at Tennessee Valley Authority's Clinch River siteGE Vernovagevernova.com
- 02Clinch River Nuclear Site ApplicationUS Nuclear Regulatory Commissionnrc.govas read on Nov 25, 2026
- 03TVA touts $1.7B data center deal under new large-load tariffUtility Diveutilitydive.com
- 04Tennessee Valley Authority Form 10-K for the fiscal year ended September 30, 2026Tennessee Valley Authority (SEC filing)sec.gov
- 05First construction permit issued for BWRX-300 SMR in the USWorld Nuclear Newsworld-nuclear-news.org
- Published
- Sources
- 5 cited