TerraPower Kemmerer Unit 1: 345 MWe Natrium Permitted, No EPC Builder Yet

TerraPower's Kemmerer Unit 1 in Wyoming holds an NRC construction permit and a PacifiCorp power purchase agreement, but has named no replacement for Bechtel as of Nov. 23.

Nuclear & Microgrids Desk

5 min read

Rendering of the planned TerraPower Natrium plant at Kemmerer, Wyoming: low plant buildings and tanks on open grassland under a blue sky

Rendering of TerraPower's Natrium plant in Kemmerer, Wyoming, as published by the U.S. Department of Energy. It is an artist's rendering, not a photograph of the site.

Image: U.S. Department of Energy

Source · U.S. federal government work, public domain

TerraPower had still not named a new lead engineering, procurement and construction (EPC) contractor for its 345 MWe Kemmerer Unit 1 in Wyoming two months after Bechtel's exit, Cowboy State Daily reported on Nov. 23, 2026.

The same day, Kemmerer's city council held a second reading of an ordinance that would make developers of temporary worker housing post bonds to pay for removing it, according to the paper. The city of 2,415 people (2020 Census, per Cowboy State Daily) is bracing for the roughly 1,600 construction workers TerraPower said in April it was mobilizing. Neither company answered the paper's questions.

On paper the project has much of what a first plant needs. It holds the first construction permit for a commercial non-light-water power reactor, which the Nuclear Regulatory Commission (NRC) calls its first commercial reactor construction approval in nearly a decade, its developer, TerraPower, announced the official start of construction on April 23, 2026, and PacifiCorp has a power purchase agreement for its output. What it lacks is the contractor that turns those pieces into a plant on TerraPower's target of completing the project in 2030. That is a construction risk first, though the operating licence application is still ahead, as Voltgrid argued when the permit count reached three.

How the Natrium Sodium-Cooled Reactor Works

Natrium is a sodium-cooled fast reactor, a TerraPower and GE Vernova Hitachi Nuclear Energy design. Liquid sodium carries heat out of the core at low pressure, and the plant stores part of that heat in tanks of molten salt rather than sending it all straight to the turbine. The NRC describes the plant as 345 MWe, with the storage able to boost output temporarily to up to 500 MWe; the reactor itself is rated at 840 MWt, a thermal figure, on the NRC's project page. The one idea that matters for buyers is that split: the reactor runs steadily while the salt tanks let the turbine follow demand, so the plant can send out more power in peak hours than its 345 MWe base output.

DOE Cost Share and the PacifiCorp PPA

The Department of Energy (DOE) backs the plant through its Advanced Reactor Demonstration Program, which TerraPower says authorizes a 50/50 cost share of up to $2 billion for the Natrium project, matched dollar for dollar by TerraPower and partners. The cost-shared scope includes design and licensing, fuel development and qualification, and two support facilities, a fuel fabrication plant and a sodium test and fill facility; no source read says how much has been paid out. Cowboy State Daily calls Kemmerer a $4 billion project; TerraPower's pages give no total cost.

The buyer is PacifiCorp, trading as Rocky Mountain Power, under a power purchase agreement (PPA) with TerraPower subsidiary US SFR Owner. Idaho regulators granted the utility a one-time waiver of their competitive-bidding rules for the PPA on May 22, 2026. The utility told Idaho that Wyoming's commission had approved its waiver, and that similar proceedings were pending in Utah, Oregon and California. These are waivers, not approvals of the PPA. The PPA was filed as a confidential attachment, so its price and term are not public, and the waiver does not let the utility recover the cost in rates without a separate prudence review.

The construction contract is the gap. Bechtel said it will remain on site to complete the Sodium Test & Fill Facility and support an orderly transition, and that its work was under an earlier phase of the contract, before the full EPC scope, according to World Nuclear News. TerraPower told the outlet that construction will keep its current schedule with subcontractors and EPC support firms already on site, and that it will rebid the contract. On Aug. 31 it announced 12 supplier awards for the plant and the sodium test and fill facility. Two weeks earlier, on Aug. 14, TerraPower selected Hyundai Engineering & Construction as EPC contractor for up to eight of its future Natrium reactors under a framework agreement, the company said; that agreement covers later units, not Kemmerer Unit 1.

NRC Construction Permit and the 2030 Target

TerraPower filed its construction permit application in March 2024, and the NRC accepted it for review in May 2024. The agency issued the final environmental impact statement in October 2025 and its safety evaluation in December 2025. On March 4, 2026, the Commission authorized staff to issue the permit, and the NRC's project page records the permit decision on March 9. A permit allows building, not running: US SFR Owner must still file a separate operating licence application, and NRC staff must approve it before the plant can operate. No source read shows that application filed. TerraPower says the project is expected to be completed in 2030, a target; a TerraPower spokesperson, quoted by the American Nuclear Society, puts commercial operation in 2031, and POWER reports US SFR Owner told the NRC it expects to finish construction by February 2031.

Kemmerer Unit 1: licensing steps done and planned

  1. Done

    Construction permit application filed

    Submitted 28 March 2024.

  2. Done

    NRC accepts the application

    Accepted for review.

  3. Done

    Final environmental impact statement

    Issued by the NRC.

  4. Done

    Safety evaluation

    Issued by the NRC.

  5. Done

    Commission authorizes the permit

    Authorizes staff to issue the construction permit; the NRC project page records the decision on Mar. 9, 2026.

  6. Done

    Construction starts

    TerraPower announces the official start of construction.

  7. Done

    Bechtel exits; EPC contract to be rebid

    TerraPower says it will rebid the EPC contract and keep the current schedule.

  8. Unconfirmed

    No replacement EPC contractor named

    No replacement named as of this date (reported by Cowboy State Daily).

  9. Unconfirmed

    Operating licence application

    Required before the plant can operate; no source read shows it filed.

  10. Scheduled

    Project completion, per TerraPower

    A target, not a commitment.

  11. Scheduled

    Commercial operation, per a TerraPower spokesperson

    Quoted by the American Nuclear Society; a target.

What Kemmerer Unit 1 Means for Data Centers

Kemmerer Unit 1 itself is utility supply for PacifiCorp's grid, not a data-center deal. Its value to AI buyers is as the first Natrium unit: TerraPower says its agreement with Meta is for up to eight Natrium plants by 2035, and Kemmerer Unit 1 is not one of them. Compare it with TVA's Clinch River BWRX-300, whose construction permit decision is dated Sept. 28, 2026. TVA has a permit but no build decision, no named partner and no disclosed construction contract. Kemmerer has a permit, a construction start and a contracted buyer, but no lead builder, no operating licence application, no confirmed first-core fuel and three state waiver rulings still pending. Voltgrid's tally of HALEU on record sets out the fuel tonnages disclosed so far.

Natrium's core is a column of metallic uranium-zirconium fuel made from high-assay low-enriched uranium (HALEU), the NRC project page says, which is enriched further than the fuel in today's water-cooled reactors. That makes fuel a schedule item next to the permit and the builder, and Natrium's fuel chain is still being assembled.

POWER reports that TerraPower is assembling the supply in four parts: enrichment by Centrus at Piketon, Ohio, metallization by Framatome in Richland, Washington, fabrication by Global Nuclear Fuel-Americas in Wilmington, North Carolina, and an ASP Isotopes enrichment project in South Africa that began as a term sheet signed Oct. 30, 2024. POWER ties the 2030-31 operation target to securing enough HALEU; none of the sources read states that the first core's fuel has been delivered.

What to Watch After Bechtel's Exit

The first marker is the name of the new EPC contractor for Kemmerer Unit 1 and whether it takes on the worker-housing proposals Bechtel had solicited; TerraPower has given no date. In Kemmerer, Target Logistics Management has until Dec. 8 to decide on a lease of more than 70 acres of city land for worker housing, Cowboy State Daily reported. After that come the remaining state rulings on the utility's waiver requests in Utah, Oregon and California, a prudence review before costs reach customers, the operating licence application, and any change to the 2030 completion target.