Minneapolis Data Center Moratorium Lapses Nov. 21 After 7-5 Veto Vote
Minneapolis's six-month pause on large data centers ended Nov. 21 with no replacement rules after the council fell two votes short of overriding Mayor Frey's veto; a new ordinance is slated for a Dec. 17 vote.
3 min read

Mayor Jacob Frey, whose veto of the data center ordinance the council failed to override on Nov. 20. Official portrait.
Image: City of Minneapolis
Source · Official portrait from the City of Minneapolis mayor's page, used for news reporting.
The Minneapolis City Council failed on Nov. 20, 2026 to override Mayor Jacob Frey's veto of its data center ordinance, voting 7-5 against the nine votes required, and the city's six-month moratorium on large data centers lapsed on Nov. 21.
The Nov. 20 override attempt fell short with nine votes needed; the next steps are a Dec. 14 planning commission hearing and a Dec. 17 council vote.
Graphic: Voltgrid News
KSTP reported that Council Member Jamison Whiting was absent for the override vote, and FOX 9 reported the same 7-5 result on the council's separate attempt to override Frey's veto on his police chief nominee. The council had passed the data center ordinance 7-6 on Nov. 12, according to the Minnesota Spokesman-Recorder, and Frey vetoed it on Nov. 19. MPR News reported that his objection was a last-minute amendment requiring case-by-case council approval of any new data center, which he said would lead to "arbitrary rule making" and a "de facto ban."
What the vetoed ordinance would have done
According to MPR News, the compromise would have limited new data centers to existing buildings in two downtown zoning districts and capped server space at 150,000 square feet. That sits between the 175,000 square feet city staff proposed and the 50,000 square feet the planning commission recommended. It would also have required mixed use of the building and required any center with more than 50,000 square feet of server space to buy into a renewable energy program. The Spokesman-Recorder added that it required disclosure of energy and water use.
Frey said he would sign the staff framework the council started from, which he called "one of the strictest data center regulatory frameworks in the country." His office told the Spokesman-Recorder that the framework requires a conditional use permit, which triggers a public hearing, and that the overlay-district amendment came from Council Member Robin Wonsley.
What rules apply now
The moratorium blocked most new data centers but exempted downtown projects under 350,000 square feet, MPR News reported. With it gone, data centers fall back under the existing zoning code, which allows them with a permit in 10 of the city's 15 zoning districts, according to MPR News and the Spokesman-Recorder.
KSTP reported that Minneapolis now has no rules on data center size, noise, energy or water use, and that the city told the station it has no data center applications pending. Council Member Soren Stevenson urged developers to hold off while the council acts. The Spokesman-Recorder reported that the council says it cannot enact another moratorium.
For power and water, the ordinance's energy and water disclosure and renewable-program buy-in are not in force. Utility terms for the largest loads are set at state level. The Citizens Utility Board of Minnesota, a consumer group, reported that the Minnesota Public Utilities Commission approved a very large customer tariff for Xcel Energy that applies at 100 MW or more of capacity, puts those customers in a separate rate class and requires a minimum 15-year contract. It also sets a minimum bill of at least 80 percent of the contracted amount. Customers between 20 MW and 100 MW can be pulled in if they need significant system upgrades.
That framework governs how a Minneapolis data center would pay for power, not where it may be built. The sources read for this story give no Minneapolis water-use figures, so none are cited here.
MPR News reported that the planning commission holds a public hearing on Dec. 14 and the council takes a final vote on Dec. 17. KSTP's account of the city attorneys' advice is that Dec. 17 is the earliest new rules can be added.
Frey's press secretary told the Spokesman-Recorder that the mayor's office expects the next proposal to reflect the staff recommendation. The text of that proposal is not yet public, so whether Frey signs it is not confirmed.
Other cities are choosing pauses. As Voltgrid reported, St. Cloud's council backed a one-year pause on a 4-3 motion on Nov. 16, and Springfield extended its moratorium 120 days to Feb. 24, 2027. Oakland's extension runs to Oct. 5, 2027, and our tracker of moratoriums, lawsuits and votes covers the wider count.
What is not confirmed yet
The text of the new ordinance has not been published in the coverage read for this story. It is unconfirmed whether it will keep the 150,000-square-foot cap, the renewable-program buy-in and the energy and water disclosure, and whether Frey will sign it.
Sources
- 01Minneapolis Data Center Moratorium Ends After Veto Override FailsMinnesota Spokesman-Recorderspokesman-recorder.com
- 02Minneapolis City Council fails to overturn mayor vetoes on police chief nomination, data center rulesFOX 9fox9.com
- 03Data center regulations will go before Minneapolis City Council again next monthMPR Newsmprnews.org
- 04Data Centers to Pay Fair Share: PUC enacts protections for Xcel customersCitizens Utility Board of Minnesotacubminnesota.org
- 05Data center regulations up for vote at Minneapolis City CouncilMPR Newsmprnews.org