NVIDIA said on Nov. 17 it signed substrate and packaging deals with Kinsus, SPIL, Amkor and others, as fiscal 2028 supply and capacity commitments reached $203B in its CFO commentary.

Chips & Power Desk

3 min read

NVIDIA Vera Rubin NVL72 rack standing open and lit from inside against a dark background

NVIDIA's Vera Rubin NVL72 rack, which the company says began volume shipments in the third quarter. The photo shows the product, not the supplier sites named in the story.

Image: NVIDIA

Source · Press image from the NVIDIA website, used for news reporting.

NVIDIA said on Nov. 17 that it signed new substrate and packaging agreements, including a more than 3.5x expansion of Kinsus's ABF substrate capacity for NVIDIA, while its fiscal 2028 supply and capacity commitments reached $203 billion.

The company named six partners in its release: Amkor Technology, Foxconn, Kinsus Interconnect Technology, Samsung Electro-Mechanics, Siliconware Precision Industries (SPIL) and TSMC. The work spans substrates, advanced packaging, wafers and contract manufacturing. It came alongside quarterly results that Voltgrid covered separately, including the China shipment halt.

The $203 billion comes from NVIDIA's CFO commentary, filed with the SEC. It is the fiscal 2028 column of a table that totals $390 billion of supply and capacity commitments, up from $279 billion a quarter earlier. The company said the increase was primarily related to multi-year procurement of memory supply. By Voltgrid's arithmetic, fiscal 2028 holds about 52% of that total, and the figure was $87 billion in the company's table as of July 26, so it rose by $116 billion in one quarter.

What Kinsus, Amkor and SPIL Agreed To

Under a new multiyear agreement, Kinsus plans to expand its advanced ABF package substrate capacity dedicated to NVIDIA by more than 3.5x over current levels at its Youth campus in Taoyuan, Taiwan. Production is expected to begin in the second half of 2027, with the added capacity targeted for the third quarter of 2028, NVIDIA said.

Samsung Electro-Mechanics amended its existing substrate supply agreement to improve operations at current factories in Sejong and Busan, South Korea. NVIDIA gave no capacity figure for that amendment.

On packaging, NVIDIA said its multiyear agreements with Amkor, announced in July and October 2026, total nearly $3 billion and include prepayments to expand capacity in Arizona and South Korea. SPIL is expanding advanced packaging in Taiwan under a multiyear agreement backed by what NVIDIA called multibillion-dollar funding from NVIDIA. That will raise contracted packaging capacity dedicated to NVIDIA by mid-2029, with new lines for bumping, interposer wafer fabrication, assembly and testing.

NVIDIA also said Vera Rubin NVL72 systems and Vera CPUs began volume shipments in the third quarter, built on TSMC's 5nm, 3nm and CoWoS advanced packaging. Foxconn, the release said, will support the volume ramp with its production network across Asia, North America and Europe.

Why NVIDIA's Supply Commitments Matter for AI Capacity

Substrates and packaging are the steps between a finished wafer and a shippable accelerator, so they set how many racks a data-center buyer can actually receive. NVIDIA is now paying to widen those steps years ahead: Kinsus's added capacity lands in 2028 and SPIL's by mid-2029. The $203 billion shows the other half of the same bet, with memory purchasing driving the jump.

The deals build on an October round with Amkor, IBIDEN, King Yuan Electronics, Samsung Electro-Mechanics, SPIL and Unimicron. NVIDIA said that round included an aggregate 2.5x increase in substrate capacity over three years, a doubling of semiconductor testing capacity from 2026 to 2027, and a 15x increase in SPIL's optical-engine capacity by mid-2027. For the memory side, see Voltgrid's AI chip supply chain roundup and its report that NVIDIA reportedly asked all three HBM makers to build base dies on TSMC 3nm.

Commitments of this size cut both ways. They secure supply, but they also fix purchasing obligations for years: the table shows $92 billion for fiscal 2029, then $10 billion for fiscal 2030, $8 billion for fiscal 2031 and $8 billion for fiscal 2032 and later.

Commitments total $390B and are front-loaded: $203B falls in fiscal 2028, per NVIDIA's CFO commentary as of Oct. 25, 2026.

Graphic: Voltgrid News

What is not confirmed yet

NVIDIA did not give dollar values for the Kinsus, Samsung Electro-Mechanics, Foxconn or TSMC agreements, and the SPIL funding is described only as multibillion-dollar. The company did not split the $203 billion by supplier or say how much of it is memory, since the line covers supply and capacity. NVIDIA's Form 10-Q for the third quarter was not yet posted when this was written, and its notes may add detail on terms. The $203 billion and $390 billion figures come from NVIDIA's own filing and were also reported by Shacknews.

Sources