Oklo Drops Power Reactor From $1.5B Indiana LEAP Site, Eyes Isotopes

Oklo says its proposed $1.5 billion project in Lebanon, Indiana will not generate electricity. It would make medical isotopes, and no final decision to build has been announced.

Chips & Power Desk

2 min read

Oklo Aurora powerhouse campus at night under the Milky Way, a wood-clad angular building with lit entrance

Oklo's Aurora powerhouse campus, from the company's newsroom. The image is illustrative and does not show the Lebanon, Indiana site.

Image: Oklo

Source · Press image from the Oklo newsroom, used for news reporting.

Oklo Inc.'s proposed $1.5 billion project in the LEAP District near Lebanon, Indiana, will not include an electricity-producing nuclear reactor, according to company materials reported on Nov. 18 and 19, 2026.

An information packet handed out at a public open house in Lebanon this week said the company is working on a facility that would include a reactor to produce radioisotopes for medical use, the Indiana Capital Chronicle reported in a story carried by The Journal Gazette. The packet said Oklo does not plan to build an electricity-producing reactor in LEAP, as quoted by The Lebanon Reporter. Oklo has not announced a decision to proceed.

Why the power question came up

The change matters for data-center power supply because the site sits in the district where Meta is building a $10 billion data center campus, according to the Capital Chronicle. The original September contract with the Indiana Economic Development Corp. (IEDC) listed "nuclear power generation, radioisotope production, research and development" as possible uses. Oklo has a separate, much larger power plan with Meta in Ohio, where it targets up to 1.2 GW of Aurora reactors by 2034, as Voltgrid reported. The Indiana site is not part of that plan, and this project adds no megawatts to any grid.

Land, money and approvals

The State Budget Committee approved an IEDC request to put $20 million toward expanding the LEAP District by 185 acres for the project, the Capital Chronicle said. The Lebanon Reporter reported that the vote on Nov. 10 was 4-1, with $8 million from the general fund and $12 million from the state's deal-closing fund. Its account says the buyer is an Oklo subsidiary, Bigfoot Metals Development, and that an initial document put the price at $160,000 per acre for about 440 acres. The IBJ reported that Oklo has revised the agreement to cap the purchase at 220 acres, and the IEDC told the Capital Chronicle it could not provide a copy of the updated agreement.

The project was filed under the code name Project Phoenix. IEDC Senior Vice President Mark Wasky told the committee that talks with Oklo were focused on radioisotopes and that water demand was understood to be fairly low, according to the Lebanon Reporter. The district spans about 6,700 acres, and the state has put about $1 billion into it, the Capital Chronicle said.

What is not confirmed yet

Oklo has not made a final commitment to build in Indiana. The investment is $1.5 billion in the open-house materials, but the Lebanon Reporter's Nov. 11 report cited $1.8 billion, and the two figures have not been reconciled. The acreage also differs by report: 440 acres in the original document, 220 acres in the revised one. We found no Oklo press release on the Lebanon site, so these points rest on the company's open-house packet and state documents as relayed by the outlets above. The project would also need local approvals.

The outlets' figures for Oklo's Indiana project differ and have not been reconciled, according to the Capital Chronicle, the Lebanon Reporter and IBJ.

Graphic: Voltgrid News

Oklo's nearest reactor milestone is in Texas, where it said DOE cleared its Groves-1 test reactor in Lockhart on Nov. 11. Watch for an amended IEDC agreement being posted publicly and for any Lebanon zoning filing.

Sources

Published
Sources
2 cited