Data Center Labor Shortage: Abilene Electricians Leave, ABC Cites 349,000

The data center labor shortage has Abilene, Texas, electricians moving to sites paying at least triple, CNBC reports; ABC's 349,000-worker 2026 hiring need covers all U.S. construction.

Chips & Power Desk

2 min read

Aerial rendering of Meta's planned Richland Parish, Louisiana, data center campus with large data halls and equipment yards

Meta's Richland Parish, Louisiana, data center, reported by CNBC as a $50 billion-plus project, shown in a company rendering rather than a photo of the Abilene sites.

Image: Meta

Source · Press image from the Meta data centers newsroom, used for news reporting.

A data-center construction labor shortage is pulling electricians and other skilled trades in Abilene, Texas, away from local contractors to AI sites that pay at least triple, CNBC reported on Nov. 28, 2026, as the Associated Builders and Contractors (ABC) puts the U.S. construction hiring need at 349,000 net new workers this year.

Master electrician Scotty Wristen told CNBC that some of his electricians left for data-center work, that one local company lost 42 workers in a single day, and that data-center jobs pay at least triple what he can offer. Local homebuilders, CNBC reported, are now competing with data-center sites for the same skilled workers.

The labor squeeze is a delivery risk for megawatts, not only a cost line. Every campus that has secured power still needs electricians to wire it, and ABC said in its January release that demand for electricians skilled in precision wiring has surged with data-center construction. About one-fifth of electricians are over 55, ABC said, and a majority of 2026 hiring demand comes from retirements rather than growth.

How Big the Construction Labor Shortage Is

ABC's model, released on Jan. 15, 2026, puts the 2026 need at about 349,000 net new construction workers and the 2027 need at about 456,000. The model links construction spending to payroll employment at roughly 3,450 jobs per $1 billion of added spending. The 349,000 figure covers the whole construction industry, not data centers alone.

ABC's model puts the U.S. construction hiring need at 456,000 in 2027, up from 349,000 in 2026, across all construction rather than data centers alone.

Graphic: Voltgrid News

Labor is also showing up in price. A Turner & Townsend report covered by CNBC on Nov. 20, drawn from more than 500 projects in 62 markets, found data-center construction costs up 13% year on year in 2026. The same report found 56% of surveyed experts calling power a major obstacle, with utility connections typically taking one to two years.

Who Is Paying to Train Data Center Workers

Skilled labor has flocked to Texas for projects such as the Stargate Project, which CNBC describes as a $500 billion effort backed by OpenAI, Oracle and SoftBank. Meta's Richland Parish, Louisiana, data center is a $50 billion-plus project, according to CNBC. Meta's $115 million American Workforce Academy runs with ABC to train and place workers at data-center sites.

What CNBC's Report Does Not Confirm

CNBC did not quantify how many workers have left Texas homebuilding or how long the shortage will last, and the pay comparison rests on one electrician's account. No project in the CNBC report was said to be delayed by a specific number of months or megawatts. Politics adds a second risk: Texas Governor-elect Gina Hinojosa has called for a statewide data-center moratorium. Voltgrid reported President Donald Trump's pledge of a "tremendous tax" on U.S. data centers built abroad, a further pressure on where projects go.