Trade Minister Johari Abdul Ghani said on Nov. 12 the disclosure duty will be written into law, but no bill text or date is public. Unused reserved capacity, he said, will still be billed.
3 min read

NVIDIA's H100 GPU, one of the accelerators named in the reporting on Malaysia's planned data centre disclosure law (product image, NVIDIA).
Image: NVIDIA
Source · Press image from the NVIDIA website, used for news reporting.
Malaysia plans to write a duty for data centres to disclose their electricity use and the number of GPUs imported into law, Trade Minister Johari Abdul Ghani said on Nov. 12, according to Bernama.
The minister spoke at the launch of the Ministry of Investment, Trade and Industry's (MITI) MySaham app in Kuala Lumpur, and again at a press conference afterwards. He said the government needs to know who the operators and hyperscalers are at each data centre and where each one is, and that 55 of the 117 approved data centre projects have begun operations.
The stage matters. Bernama and The Star wrote that the requirement "will be embedded" in law, while The Vibes described a proposed framework the government is "considering". None of the reports we read gives a bill text, a date for tabling it or an effective date, so for now this is a minister's stated plan, not a law.
What the Ministry Wants Operators to Disclose
Johari named four items: who operates each data centre, which hyperscalers use it, where it is, and the electricity it uses together with the number of GPUs imported. The Vibes reported that companies planning to build data centres would have to declare their operators, locations and the number of GPUs they intend to import. Bernama said separately that the Digital Ministry is reviewing existing laws to see whether they can be used against re-exports of GPUs that fall under US sanctions.
The minister did not say that power data would be used to spot smuggling. That link comes from Tom's Hardware, which argues that power draw can flag gaps between imports and operations but cannot reliably count accelerators: NVIDIA's H100 and H200 SXM GPUs are rated at 700 W and its B200 SXM at 1,000 W, and neither necessarily draws its rated power under real workloads. Tom's Hardware also notes that Johari did not say whether operators would have to report GPU models and serial numbers, or whether officials would inspect sites. Voltgrid reported on Oct. 28 that Malaysian customs seized 30 AI servers worth 49.5 million ringgit at Kuala Lumpur airport.
Billing for Capacity Nobody Uses
On supply, Johari said operators must work out the capacity they actually need, because suppliers have to allocate the capacity agreed in the supply agreement. His example: a data centre that books 100 MW but uses 50 MW will still be billed for the other 50 MW. The aim, he said, is to curb capacity reservations that might not be used for one to three years.
In the minister's example, a data centre that books 100 MW and uses 50 MW is still billed for the other 50 MW.
Graphic: Voltgrid News
The reports do not say whether this billing is part of the planned law or follows from existing supply agreements. Tom's Hardware presents it as a new charge. If the charge is new, a developer that reserves capacity early for a later phase would pay for it from the start. Malaysia approved a 30% renewable energy requirement for data centres on Oct. 27, and the guidelines were still being drafted when Voltgrid reported it, so operators face several rules whose start dates are open.
What Is Not Confirmed Yet
The Vibes reported on Nov. 12 that Johari said the government had no plans to open an investigation into Speedmatrix, the Malaysian unit of Singapore-based Megaspeed. On Nov. 13, MITI said it was working with customs to check whether Speedmatrix's chips were re-exported, as Voltgrid reported. Re-exporting high-performance US AI chips already needs a MITI permit under the Strategic Trade Act 2010, a rule in force since July 2025.
Still open: the bill's text and timetable, whether disclosure applies at the application stage or during operation, whether GPU models and serial numbers are covered, and whether the unused-capacity charge is new. Watch for a tabling date and for MITI to publish the rules.
Sources
- 01Requirement To Disclose Data Centre Operations Information To Be Embedded In LawBernamabernama.com
- 02Malaysia plans new law using data center power consumption to catch AI GPU smugglersTom's Hardwaretomshardware.com
- 03Malaysia moves to tighten data centre controls amid scrutiny over Nvidia chip exportsThe Vibesthevibes.com
- 04Keeping tabs on data centresThe Starthestar.com.my
- Published
- Sources
- 4 cited