Google Farciennes Data Center: Wallonia Halts 30,000 m² Build

Walloon officials gave Google a verbal stop order on Nov 26 at its Farciennes site in Belgium, where a 30,000 m² building was nearly finished despite a refused permit change.

Chips & Power Desk

3 min read

Aerial view of Google's Saint-Ghislain data center in Belgium, with cooling units, a substation and a solar field beside a road and rail line

Google's data center at Saint-Ghislain, Belgium, in an earlier official photo. It is not the Farciennes site, where work is now halted.

Image: Google

Source · Press image from the Google data centers pages, used for news reporting.

Walloon planning officials gave Google a verbal order on Nov 26 to stop work at its Farciennes data center site near Charleroi, Belgium, where they found a nearly finished 30,000 m² building and about 300 workers, RTBF reported.

Raphaël Stokis, the Walloon Region's delegated official, told RTBF that inspectors found the 3-hectare building with its shell already closed, even though the regional minister had refused the permit change it relies on. He said the verbal order will be confirmed in writing to Google. In a short statement quoted by RTBF, Google said it is committed to open, collaborative dialogue with the regional government and experts on its investments in Wallonia.

Why the halt matters for capacity

A halt at a building this far along pushes back the date a large hall can take servers and draw grid power. The sources give no megawatt figure for the site, so the capacity at stake is unknown. What they do show is that water supply, not only electricity, can decide whether a European campus gets built as designed. Google had planned to cool the larger building with water from the nearby Sambre river instead of air, and that cooling change is what the minister rejected.

How the permit dispute unfolded

Google held a 2024 permit for three smaller, air-cooled data centers at the site, according to ITdaily and RTBF. It then asked to merge two of them into one much larger building and to switch to river-water cooling. ITdaily reported that the Walloon administration approved that amendment in April and that a citizens' appeal followed a month later. In August 2026, François Desquesnes, the minister for spatial planning (Les Engagés), refused the amendment, citing the data center's water needs. Google took the matter to the Council of State, Belgium's top administrative court, which will hear the appeal on Jan 7, 2027.

The verbal stop order of Nov 26 comes before the Council of State hears Google's appeal on Jan 7, 2027, according to RTBF and ITdaily.

Graphic: Voltgrid News

Greenpeace says Google kept building in the meantime. Based on satellite images, the group argued the work simply continued, and on Wednesday, Nov 25, it started an urgent procedure with the Walloon administration to stop the site, according to ITdaily, citing RTBF.

The minister's cabinet says the original 2024 permit remains valid, so Google may build under it but not under the amended plans. Officials are checking whether the work under way matches that permit. If they find violations, an official report will follow and go to the public prosecutor's office, ITdaily reported.

The site and Google's Belgian footprint

Google builds through its European subsidiary Crystal Computing on the Ecopôle business park, which spans Farciennes, Aiseau-Presles and Sambreville. The site covers 53 hectares, the company bought the land in 2021, and it announced an additional EUR 1 billion investment when construction started, according to ITdaily. Greenpeace ties the project to Google's water use at Saint-Ghislain near Mons, claiming a comparable data center there pumps about 1 billion litres a year for cooling and returns only a quarter of it. That figure is the NGO's claim, and Google has not answered it publicly.

Permit trouble has stopped another Google project this week. Voltgrid News reported on Nov 25 on Google's Van Buren campus in the United States, halted over a county permit; it is a different site under a different authority.

What is not confirmed yet

The written stop order had not been published in the sources read, so its exact scope is unconfirmed, including whether it covers only the merged building or all construction at the Ecopôle. The Walloon government's own notice was not available to read, and the account here rests on RTBF and ITdaily, which cites VRT NWS. The two outlets differ on when Google filed its amendment request (2024 in RTBF, 2025 in ITdaily), so Voltgrid News gives no year. The inspection result, a possible report to prosecutors, Greenpeace's urgent procedure and the Council of State hearing on Jan 7, 2027 are all pending.

Sources

Published